Follow Us:

Case Law Details

Case Name : Aastha And Saumya Construction Vs State of Bihar (Patna High Court)
Related Assessment Year :
Become a Premium member to Download. If you are already a Premium member, Login here to access.

Aastha And Saumya Construction Vs State of Bihar (Patna High Court)

Patna HC Directs Decision on Contractor Claims Due to Pending Representations; Contractor Seeks Foreclosure Due to Land Issues; Patna HC Issues Directions; Patna HC Directs Bihar Authorities to Consider Road Work Payment Claims; Pending Land Acquisition Led to Contract Dispute, Patna HC Intervenes.

The Patna High Court disposed of a writ petition filed by a contractor seeking multiple reliefs relating to a road construction agreement executed under the Road Construction Department, Government of Bihar. The project concerned widening and strengthening of the Jariso Chowk (SH-88) to Bharat Chowk (SH-56) bypass road under RCD Road Division, Benipur. The petitioner sought foreclosure of the agreement on the ground that complete land was not made available for execution of work, landowners were allegedly obstructing construction activities, and the cost of labour and materials had increased substantially over time.

Apart from foreclosure of the contract, the petitioner sought payment for various alleged additional and unpaid works. These included compensation for difference in soil work caused by excavation undertaken by private landowners, payment for additional leveling work not incorporated in the original estimate, and reimbursement of extra carriage charges for transportation of sand due to restrictions on movement of heavy vehicles over Rajendra Bridge. The petitioner also claimed payment for widening work and DLC work allegedly performed beyond the scope of the original estimate.

Further claims included payment under Clause 10CC on account of escalation during the period in which land acquisition remained pending, reimbursement of differential GST liability from 12% to 18% for certain running account bills, refund of Rs. 49 lakh deducted from running account bills towards time extension, payment of the entire amount allegedly due along with penal interest at 18%, litigation costs, and protection against coercive action by the authorities.

During the hearing, counsel for the petitioner submitted that the grievances had already been raised before the authorities through representations dated 21.04.2025 and 23.03.2026 addressed to the Additional Chief Secretary, Road Construction Department, Government of Bihar. It was contended that no steps had been taken by the authority to dispose of those representations. The petitioner therefore requested the Court to direct the authority to consider the representations within a fixed time frame.

The High Court observed that without entering into the merits or demerits of the claims raised in the writ petition, the matter could be disposed of at the admission stage with consent of both parties. Accordingly, the Court directed the Additional Chief Secretary, Road Construction Department, Government of Bihar, to consider and dispose of the petitioner’s representations dated 21.04.2025 and 23.03.2026 expeditiously, preferably within six weeks from receipt of a copy of the order.

The Court further directed that before passing any order, the petitioner must be given an opportunity of hearing and that any decision taken should be communicated to the petitioner. The writ petition was accordingly disposed of with liberty to the petitioner to furnish a copy of the Court’s order along with a fresh representation, if so advised.

FULL TEXT OF THE JUDGMENT/ORDER OF PATNA HIGH COURT

Heard learned counsel for the parties.

2. The present writ petition has been filed for the following relief(s):-

“I. For directing and commanding the responding authorities to foreclose the agreement bearing agreement no. 5 SDB/2022-23 namely Widening & Strengthening of Jariso chowk (SH-88) to Bharat Chowk (SH-56) Bypass road (via. Dakhram- Pauri- Mushahari-Dipa-Barmajha Pokhar-Pohaddi) in KM 0.00 to 5.550, under RCD Road Division, Benipur, pursuant to their decision taken (Letter of Acceptance) vide memo no. 77 dated 27.01.2023, moreover, till date neither entire land is available for performing the work, nor the land owners are allowing to carry out the work and due to passage of long time the price of labor, material and the cost has increased leaps and bounds.

II) For directing and commanding the responding authorities for making payment of difference of soil work, from estimated value, as private land owners have excavated approximately 4000M3 of soil from the level at which the calculation table of earth work is taken in the project estimate, using JCB.

III) For making payment of work of leveling which was not incorporated in the estimate of work in question, provision for leveling from 02KM in GSB, had not been made and during execution of work it was required additional leveling work was directed to be performed and total leveling work performed by the petitioner was 400M3 GSB material, out of which only payment of 13M3 was made and remaining 387M3 is required to be paid to the petitioner.

III(A). For making payment of extra carriage charges as in the estimate provision has been made of carriage of sand by road from Lakhisarai via Rajendra Bridge, but due to the construction of Rajendra Bridge, the movement of heavy vehicles were banned for last five years, due to which additional carriage of about 67KM has been done via Munger by the petitioner.

IV). For making payment of cost of widening of 1165M and in 1KM DLC work, which was directed to be performed by the petitioner and accordingly was done by the petitioner and payment was not made as there was no provision in the estimate, and also payment of 2 feet, 10 inches widening, 1169 GSB, 1000M GSB+DLS.

V) For directing and commanding the respondent authorities for making payment after giving benefits of clause 10CC, as there was no land available for carrying out the work further, allotted to the petitioner since, there is still acquisition of land is pending.

VI). For making payment of difference of amount of GST from 12% to 18%, as from 12th running on account bills to 15th running on account bills, an amount of 18% was made by the petitioner.

VII) For making payment of an amount of Rs.49,00,000/- (forty nine lakhs) which was deducted from the running on account bills of the petitioner in the name of time extension.

VIII) For restraining the respondent authorities from taking any coercive action as against the petitioner pursuant to agreement no. 05 SBD/2022-23.

IX) For making payment of entire amount of the work done by the petitioner along with penal interest @18% from date it became dues, till actual date of payment.

X) For making payment of cost of litigation taking into consideration the fact that due to malicious and biased attitude of the respondent authorities and petitioner has been compel to approach before this Hon’ble court.

XI) For any other relief or reliefs for which the petitioner is entitled under law in the facts and circumstances of the present case.”.

3. Without going into the merits or demerits of the case, the present writ petition is disposed of at the stage of admission with the consent of both the counsels.

4. Learned counsel appearing on behalf of the petitioner submits that the petitioner has already ventilating his grievance by way of representations dated 21.04.2025 and 23.03.2026 to the Respondent No. 2, i.e., the Additional Chief Secretary, Road Construction Department, Government of Bihar (Annexure P/10 series) but the authority till date has not taken any steps to dispose of the same. Learned counsel therefore prays that a direction may be given to the Respondent No. 2 to consider the said representations and take necessary action in accordance with law by fixing a time frame.

5. Having regard to the above made submissions, the present writ petition is disposed of directing the Respondent No. 2, i.e., the Additional Chief Secretary, Road Construction Department, Government of Bihar to consider the representations dated 21.04.2025 and 23.03.2026 (Annexure P/10 series) made by the petitioner as expeditiously as possibly preferably within a period of 6 weeks from the date of receipt of a copy of this order.

6. It is needless to mention that before passing any orders, the petitioner shall be given an opportunity of hearing. Any order passed shall be communicated to the petitioner.

7. With the above directions, the present writ petition stands disposed of.

8. The petitioner is granted leave to furnish a copy of the present order along with a fresh representation, if he is so advised.

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

Leave a Comment

Your email address will not be published. Required fields are marked *

Ads Free tax News and Updates
Search Post by Date
May 2026
M T W T F S S
 123
45678910
11121314151617
18192021222324
25262728293031