Sponsored
    Follow Us:

Case Law Details

Case Name : M/s. Ramsukh Properties Vs. Dy CIT (ITAT Pune)
Appeal Number : I.T.A. No. 84/PN/2011
Date of Judgement/Order : 25/07/2012
Related Assessment Year : 2007-08
Become a Premium member to Download. If you are already a Premium member, Login here to access.
Sponsored

Assessee is a firm engaged in business of builder and promoter. The issue before us is regarding allowability of deduction u/s.80IB(10) of the Act on partially complete project. The Assessing Officer has denied the deduction on the ground that project was not complete within the stipulated time. There is no dispute with regard to other conditions laid u/s.80IB(10) of the Act,

i.e., commencement of project, area of land of project, etc. Assessee’s housing project was approved vide commencement certificate No.3837/04 dated 13.01.2005 out of which completion certificate was obtained and furnished before the Assessing Officer for 173 out of 205 flats. Same was rejected by the Assessing Officer and confirmed by the CIT(A). The request for granting whole deduction in respect of whole project has rightly been rejected because deduction u/s.80IB(10) could not be granted to assessee on incomplete construction at relevant point of time. Regarding proportionate deduction in respect of 173 of 205 flats of project completed as recognized by local authority, i.e., PMC in its completion certificate No.BCO/03/01333 dated 31.03.2008, the Ld. Authorised Representative heavily relied on decision of Bengal Ambuja Housing Development Ltd. (supra), Brigade Enterprises P. Ltd. (supra), AIR Developer (supra), Sheth Developers (supra) and also G.V.Corporation (supra), wherein deduction u/s.80IB(10) was denied as size of some of the residential units exceeded prescribed limit as laid down u/s.80IB(10) of the Act. Above mentioned decisions are applicable in their own sphere, i.e. on point of excess area of some of the flats which hold good in its own sphere. However, in case before us, deduction u/s.80IB(10) of the Act has been rejected on the ground that condition of completion of project before the due date i.e., 31.03.2008 as laid down u/s.80IB(10)(c) of the Act, has not been complied by assessee which is basic condition for allowability of deduction u/s.80IB(10) of the Act. We find that in case of Johar Hassan Zojwalla (supra), wherein condition of completion as laid down in section 80IB(10)(a) could not be complied with because of a stay being granted by MRTP Court. Thus fault of incompletion of construction was not attributable to assessee. In case such a contingency emerges which makes the compliance with provision impossible, then benefit bestowed on an assessee cannot be completely denied. Such liberal interpretation should be used in favour of assessee when he is incapacitated in completing project in time for the reasons beyond his control. In case before us, as stated on behalf of assessee, that assessee submitted certain modifications/rectifications for top floors of building. The said modification/rectification could not be completed as local authority could not approve the modification as their files have been taken over by concern intelligence department for investigation of violation of urban land ceiling Act applicable to land in question at relevant point of time. This fact has not been disputed on behalf of revenue. Thus, assessee was prevented by sufficient reasonable cause which compelled the impossibility on part of the assessee to have completion certificate in time. It is settled legal position that the law always give remedy and the law does wrong to no one. We agree to proposition put forward by Ld. Departmental Representative that plain reading of section 80IB(10) of the Act suggests about only completion of construction and no adjective should be used alongwith the word completion. This strict interpretation should be given in normal circumstances. However, in case before us, assessee was prevented by reasonable cause to complete construction in time due to intervention of CID action on account of violation of provisions of Urban Land Ceiling Act applicable to land in question. Assessee was incapacitated to complete the same in time due to reasons beyond his control. Assessee should not suffer for same. The revision of plan is vested right of assessee which cannot be taken away by strict provisions of statute. The taxing statute granting incentives for promotion of growth and development should be construed liberally and that provision for promoting economic growth has to be interpreted liberally. At the same time, restriction thereon too has to be construed strictly so as to advance the object of provision and not to frustrate the same. The provisions of taxing statute should be construed harmoniously with the object of statue to effectuate the legislative intention. In view of above facts and circumstances, we hold that assessee is entitled for benefit u/s.80IB(10) of the Act in respect of 173 flats completed before prescribed limit. The Assessing Officer is directed accordingly.

INCOME TAX APPELLATE TRIBUNAL , PUNE

I.T.A. No. 84/PN/2011 : A.Y. 2007-08

M/s. Ramsukh Properties Vs.  Dy CIT  

Please become a Premium member. If you are already a Premium member, login here to access the full content.

Sponsored

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

Leave a Comment

Your email address will not be published. Required fields are marked *

Sponsored
Sponsored
Search Post by Date
July 2024
M T W T F S S
1234567
891011121314
15161718192021
22232425262728
293031