Follow Us:

Case Law Details

Case Name : Sensation Viietha Infra Developers Vs State of Telangana (Telangana High Court)
Related Assessment Year :
Become a Premium member to Download. If you are already a Premium member, Login here to access.

Sensation Viietha Infra Developers Vs State of Telangana (Telangana High Court)

The Telangana High Court adjudicated a writ petition challenging the inaction of the Commissioner of Police, Rachakonda, in not disposing of an application dated 25 August 2022 for grant of a No Objection Certificate (NOC) for construction of a multiplex theatre and shopping mall in Narapally Village, Medchal-Malkajgiri District. The petitioner, a partnership firm, had entered into development agreements-cum-General Power of Attorney (GPA) with landowners through registered documents executed in July and September 2019, granting development rights with a sharing ratio of 60:40.

The petitioner submitted that, as a GPA holder with irrevocable rights under valid development agreements, it was entitled to apply for NOC without requiring separate consent from the landowners. It argued that any disputes with landowners or third parties must be resolved before a civil court or arbitrator and cannot justify indefinite withholding of its application. It was also contended that under the applicable rules, the application ought to have been decided within 45 days, and failure to do so could attract deemed permission, though the petitioner preferred formal approval due to the scale of the project.

The landowners contended that the petitioner had violated the terms of the agreements and that steps had been taken to cancel them, including issuance of a legal notice. Another respondent claimed independent rights and raised concerns about adverse impact on his interests. The State authorities argued that the petitioner was not in lawful possession of the property due to alleged cancellation of agreements and dissolution of the partnership firm.

The Court examined the record and noted that although notices had been issued by landowners seeking cancellation of development agreements, no competent court had passed any order confirming such cancellation. It held that mere issuance of notices does not amount to legal termination of agreements or dissolution of the partnership. The Court further observed that there were no prohibitory or injunction orders in force restraining the petitioner from proceeding with the project. Consequently, the contention that the petitioner was not in lawful possession lacked legal basis.

The Court clarified that it was not the appropriate forum to adjudicate disputes between the petitioner, landowners, or third parties, and such issues must be resolved through civil or arbitral proceedings. In the absence of any judicial restraint order, administrative authorities could not indefinitely keep the application pending.

In its order, the Court directed maintenance of status quo for a period of four weeks. During this time, the landowners and concerned respondents were granted liberty to approach appropriate forums such as civil courts, arbitral tribunals, or commercial courts to seek interim relief. The Court further directed that if no injunction or interim order is obtained within this period, the Commissioner of Police must consider and dispose of the petitioner’s application for grant of NOC within two weeks from receipt of a reminder. The Court also clarified that any proceedings initiated before other forums should be decided independently without being influenced by its observations.

The writ petition was accordingly disposed of, with no order as to costs, and pending miscellaneous applications were closed.

FULL TEXT OF THE JUDGMENT/ORDER OF TELANGANA HIGH COURT

This writ petition is filed to declare action of respondent No.2-Commissioner of Police, Rachakonda, in not disposing of the application of the petitioner dated 25.08.2022 for grant of ‘No Objection Certificate (NOC)’ for construction of multiplex theatre and shopping mall in Survey Nos.36/1/1, 36/1/2, 37, 37/1/1/1, 37/1/2, 38/1/1/1 and 38/1/2, admeasuring 8903.01 sq. meters, of Narapally Village, Ghatkesar Mandal, Medchal-Malkajgiri District, in terms of Rule 8B of the Telangana Cinemas (Regulation) Rules, 1970 (for shod, ‘the Rules’), as illegal, arbitrary and violative of Articles 14 and 19 of the Constitution of India, and to consequently direct respondent No.2 to dispose of the said application of the petitioner.

2. The petitioner is a registered partnership firm consisting of two partners namely Nis. Sensation Infracon Private Limited and M/s. Vijetha Infra Projects. The petitioner entered into development agreement with the landowners-respondent Nos.6 to 18 wde development agreement-cum-GPA bearing document No.7375 of 2019 dated 12.07.2019 in respect of the land to an extent of Ac.1.00 in Sy.Nos.38/1/2, 3811/111, 37/1/2 and 37/1/1/1, and the development agreement-cum-GAP bearing document No.9822 of 2019 dated 11.09.2019 in respect of the land admeasuring Ac.1.08 guntas in Sy.Nos.36/1/2, 38/1/1, 36/1/1 and 36/1/1. As per the terms of the said development agreements, the sharing ratio between the petitioner and the landowners is 60:40. That in terms of the said development agreements, the petitioner made an application to respondent No.2 on 25.08.2022 for grant of NOC under Rule 8 of the Rules. The said application was forwarded to respondent Nos.3 to 5 for report vide proceedings dated 12.09.2022. The grievance of the petitioner is that when they approached the authorities seeking informal on about the status of their application, they were informed to get NOC from the landowners and their application is kept pending without approval in terms of the provisions of Rule 8 of the Rules.

3. Heard Mr. T. Bala Mohan Reddy, learned counsel for the petitioner, learned Assistant Government Pleader for Home appearing for respondent Nos.1 and 2, learned Assistant Government Pleader for Revenue appearing for respondent No.3, learned Assistant Government Pleader for Medical & Health appearing for respondent No.4, Mr. V. Narasimha Goud, learned Standing Counsel appearing for respondent No.5, Mr T. Venkat Reddy, learned counsel appearing for respondent Nos.6 to 18 and Mr. G. Shashidhar Reddy, learned counsel appearing for respondent No.19.

4. Learned counsel for the petitioner submitted that in the capacity of GPA holder under the aforesaid two registered documents, the petitioner submitted application for NOC, as such, there is no requirement to get NOC from the landowners. If there is any dispute between the landowners and the petitioner-developer, the appropriate remedy lies before the civil court. The said two registered documents give absolute rights to the petitioner-developer to act on behalf of the landowners, as such, there is a consent from the landowners, and not only that, the petitioner is given irrevocable rights to develop the property by constructing a multiplex theatre. So long as the two development agreements are in force, the petitioner cannot be restrained to pursue the application for NOC submitted on behalf of the landowners. Learned counsel further submitted that the application for NOC has to be disposed of within a period of 45 days, and if such application is not disposed of within such time, the petitioner is entitled to proceed with the development under deemed permission clause. However, as huge multiplex is being proposed to be constructed, the petitioner did not want to take any risk and wanted a regular permission to be obtained.

5. Mr. T Venkat Reddy, learned counsel appearing for landowners-respondent Nos.6 to 18, submitted that the petitioner did not adhere to the terms and conditions of the said two development agreements and necessary legal steps are being taken to cancel the said agreements. Learned counsel also submitted that the landowners have issued legal notice dated 26.07.2022 to the petitioner firm cancelling the two registered development agreements and the petitioner got issued reply dated 03.09.2022 to the legal notice issued by the landowners.

6. Mr. G. Shashidhar Reddy, learned counsel appearing for respondent No.19, submitted that it was respondent No.19 who negotiated the deal with the landlowners, however, ignoring his interest, the petitioner is proceeding with the construction. The rights of respondent No.19 would be adversely affected if any orders are passed by this Court.

7. In response thereto, learned counsel for the petitioner submitted that the dispute if any between the petitioner and respondent No.19 has to be adjudicated before an Arbitrator in terms of clause 15 of the partnership deed dated 18.05.2019. So also the learned counsel states that unless there is any prohibitory or injunction order passed by the civil court, the police or HMDA cannot keep the application of the petitioner in abeyance for an indifinite period.

8. Learned Assistant Government Pleader for Home, based on the written instructions, submitted that as per sub-Rule (c) of Rule 88 of the Rules, applicant should be in lawful possession of the subject site. The MOU entered with the landowners was cancelled and there is dissolution of firm.

9. It is stated by the learned counsel for respondent No.19 that notice has been issued by respondent No.19 for dissolution of partnership firm.

10. As seen from the record, a notice has been issued by the landowners to the petitioner cancelling the development agreements, but so far no order is passed by the Court. Mere issuance of notices cannot be treated as cancellation of the development agreements-cum-GPA or the dissolution of partnership firm. As of now, it is not in dispute that there are no prohibitory orders or restraint orders passed by any civil court. Thus, the contention of respondent No.2 that the applicant-petitioner is not in lawful possession of the subject site is without any legal basis. The petitioner claims to be in possession of the subject property on the strength of two registered development agreements-cum-GPA. However, this Court is not the forum for adjudication of the disputes if any between the landowners and the partners of the petitioner firm.

11. In the circumstances, the writ petition is disposed of directing status quo to be maintained for a period of four (04) weeks from today. Within this time, the landowners-respondent Nos.6 to 18 and respondent No.19 are given liberty to approach the Civil Court/Arbitrator/Commercial Court, as the case may be, by filing a suit or petition under Section 9 of the Arbitration and Conciliation Act, 1996, and seek interim orders against the petitioner. It is made clear that such suits/applications, if any filed, shall be decided on merits without being influenced by any of the observations made in this order. If there is no injunction/interim order passed by the Civil Court or Commercial Court in favour of the unofficial respondents or that the unofficial respondents have not approached the Civil Court/Commercial Court, then respondent No.2 shall consider the application of the petitioner for grant of NOC for construction of multiplex theatre in the subject property, within a period of two (02) weeks from the date of reminder that may be submitted by the petitioner.

As a sequel thereto, miscellaneous applications, if any, pending

in the writ petition stand closed. No order as to costs.

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

Leave a Comment

Your email address will not be published. Required fields are marked *

Ads Free tax News and Updates
Search Post by Date
April 2026
M T W T F S S
 12345
6789101112
13141516171819
20212223242526
27282930