Sponsored
    Follow Us:
Sponsored

Important Judgements arising out of Real Estate (Regulation and Development) Act, 2016

Introduction 

The RERA Act, 2016 is a comparatively recent legislation. The provisions established have been done so with due diligence to all possible legal scenarios and a wide pallet of recourses have also been mentioned. That being said, disputes still arise due to the advancement in transaction methods, technology, market factors and so on.

Since it is not possible to amend the legislation frequently, orders passed as part of judgement would hold good vis-à-vis application. The ratio decidendi in the below mentioned landmark cases have shaped the RERA Act and real estate laws to what we witness this day.

1. Emaar Mgf Land Ltd Co & Anr v. Aftab Singh (2017) 

The petitioner is a builder enterprise which entered into an agreement with the respondent and other persons to build flats. An agreement was entered into and the work had begun. The builder was unable to finish the completion of the building within the stipulated time. With reference to an arbitration clause mentioned in the aforementioned agreement, the builder made reference to this clause and suggested that the parties settle the matter in a court of arbitration. The respondents did not agree and filed a complaint under the Consumer Protection Act. The builder contended the same stating jurisdictional reasons i.e., the present dispute is one regarding real estate and it would fall within the ambit of the RERA Act and not the Consumer Protection Act. This legal question was the bone of contention in the case.

Ratio Decidendi: Persons who consume the services of builders have the right to seek redressal under the Consumer Protection Act and also under the RERA Act.

2. Vinod Kumar Aggarwal v. Jaipur Development Authority (2020)

Section 13 of the RERA Act states that the promoter shall not be entitled to anything more than 10% of the transaction value and this shall be payable only after the terms and conditions of the agreement have been fulfilled. The bone of contention in the present case was whether the central law which is the RERA Act would prevail over a local law with regards to the terms of an agreement and place of construction. The area where the construction was planned was not technically approved by the local authority which is the Jaipur Development Authority. The said agreement quoted for a price which exceeded the standard 10%. These were the contentions which were addressed.

Ratio Decidendi:

1. The RERA Act would prevail over the local law regarding real estate transactions.

2. The agreement must be executed mandatorily before any made is to be made.

3. Vishal Arya v. Unitech Ltd (2013) 

This case essentially was dealt in the consumer forum as the RERA Act had not come into the picture during the initial proceedings. When an allottee and a builder enter into a standard for of agreement, there exists a clause based on the concept of force majeure. This essentially means that due to external and unavoidable circumstances, the agreement cannot be executed. The present case relates to an instance where the petitioner had entered into an agreement with the respondent and had already paid the price as well. But the construction work had not yet begun. When asked, the respondent stated the reason of force majeure. This was contested in the Consumer forum and the first appeal was held under the provisions of RERA Act stating that the petitioner must be refunded with the price paid by him with three-months interest.

Ratio Decidendi: The clause of force majeure cannot be claimed unless some part of the agreement has already been fulfilled.

4. Wg. Cdr. Arifur Rahman Khan and Aleya Sultana and Ors. v. DLF Southern Homes Pvt. Ltd. (2019) 

The respondents in the present case, entered into an agreement to build homes within a stipulated time of three years and had procured the money from all the allottees in advance. Upon the expiry of such period, the respondent showed no signs of the completed flats. Therefore, the petitioners prayed that they be reimbursed with the money spent and that an additional interest be levied for the unnecessary delay. The respondents claimed that they could not claim anything.

Ratio Decidendi: When the builder does not handover the property within stipulated time without requesting any extension, then such action shall be monetarily penalised.

5. Avinash Saraf, Neha Saraf v. Runwal Homes Pvt Ltd. (2017)

The petitioners in this case contended to claim compensation for the non-delivery of property within the stipulated time. Now, this has been discussed in earlier cases as well. The bone of contention in the present case arises from a statement made by the respondent. The respondents claim that the provision for compensation would be available under Section 79 of the RERA Act but the agreement signed between the parties was in the year 2014, which was before the Act came into existence. Therefore, the bone of contention is regarding the jurisdiction of RERA Act with regard to its applicability.

Ratio Decidendi: RERA Act would apply retrospectively only in cases where the allottees are aggrieved by the actions of the builders or the promoters.

6. Sanjeev Dhakar Vs. M/s. Arkanade Realty 

The petitioner in this case had paid the builder for a house in an apartment complex. The agreement was signed between them and executed as well by both parties. What becomes the issue is the parking space which was to be allotted to the petitioner. The parking space was not provided and the same was actually sold to another allottee. The petitioner contended this.

Ratio Decidendi: When a builder takes up a project to provides apartment complexes, the allottees must also receive their assigned parking spaces, it would fall under the ambit of the RERA Act.

7. Geetanjali Aman Construction Vs Hrishikesh Ramesh Paranjape 

The bone of contention for the present case is with regards to the interpretation of Section 3(2) of the RERA Act. The provision deals with the registration of estate and what would be considered as the qualifying conditions. The section states the ‘a plot which does not exceed 500 sq. ft. or the building does not exceed eight floors’. The question of interpretation came into picture as there was a disputed estate with 9 floors.

Ratio Decidendi: The interpretation of clauses regarding conditions to be fulfilled must be read in their truest form.

8. Sushil Ansal v. Ashok Tripathi, Saurabh Tripathi (2020) 

This case is a unique one as it talks about the credit factor of a builder. In the instant case, the builder was declared bankrupt and they owed money to allottees to a tune of Rs. 73 Lakhs. This meant that the allottees would be legally called financial creditors to the builder. The bone of contention here is, where can these creditors seek redressal from.

Ratio Decidendi: When an allottee is also a creditor to the builder, he may seek redressal only under the RERA Act for cancellation/refund and consumer forum.

9. Jitendra Jagdish Tulsiani vs. Lavasa Corporation Ltd (2018)

The contention of the present case relates to a specific type of transfer of property-lease. RERA Act does not specifically mention what type of transfer comes under its jurisdiction. Therefore, the authorities themselves dismissed the above-mentioned petition.

Ratio Decidendi: RERA Act is applicable with the transfer of immoveable property and the regulation of the same. Leasing is a type of transfer and it would come under the ambit of the RERA Act.

10. Rakesh Kumar Gupta Vs. Ansal API (2017)

The RERA Act aims to protect the allottees first and only then the builders and promoters. But there have been instances, where the builders and promoters have to be protected due to a multitude of reasons. The present case relates to an instance where the allottee delayed in the possession of the property by 45 days. This cost the promoter some expenses on maintenance which was huge.

Ratio Decidendi: If the allottee delays in occupying the property, then the allottee must pay a 10% interest on the transactional value as compensation.

This blog is written by Supraja Sheshadri, an intern of Smriti Legal LLP.

Sponsored

Tags:

Author Bio

Smriti Legal LLP is a sector focused law firm headquartered at Bengaluru with associated offices nationwide. The firm specializes in RERA litigation and legal advisory services under The Real Estate (Regulation and Development) Act, 2016 (www.smritilegal.com) Contact: +91 97400 12005 View Full Profile

My Published Posts

From Legal Uncertainty to Clear Guidelines: Judicial Mandate for Karnataka’s Apartment Associations Builders Ordered to Hand Over Common Areas to Homebuyers: KRERA TS RERA Circular Promotes Real Estate Project Transparency & Accountability Supreme Court Declares Homebuyers as Creditors under IBC Battle of Vahe Imperial Gardens: Consumers Triumph over Deceptive Real Estate Developer View More Published Posts

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

One Comment

  1. Ojaswi Gupta says:

    Can a buyer (who has already approached RERA against a builder and has got a favourable order giving him a refund with interest)

    Appeal against that order to seek a re allotment in a different project ?

    He basically wants another property instead of a refund.

Leave a Comment

Your email address will not be published. Required fields are marked *

Sponsored
Sponsored
Sponsored
Search Post by Date
October 2024
M T W T F S S
 123456
78910111213
14151617181920
21222324252627
28293031