Case Law Details
In re Achampet Solar Private Limited (GST AAR Telangana)
Whether liquidated damages recoverable by the applicant from Belectric India on account of delay in commissioning, qualify as a ‘supply’ under the GST law, thereby attracting the levy of GST?
In the case of the applicant, liquidated damages are imposed for covering the loss of revenue and costs borne by a project SPED due to delay according to a formula. Thus liquidated damages are claimed by the applicant from the contractor due to the delay in commissioning of the project and the taking over date by the contractor beyond the milestones fixed for completion of project. These damages are consideration for tolerating an act or a situation arising out of the contractual obligation. The entry in 5(e) of Schedule II to the CGST Act classifies this act of forbearance as follows:
5(e): Agreeing to the obligation to refrain from an act, or tolerate an act, or a situation, or to do an act.
Further Section 2(31)(b) of the CGST Act mentions that consideration in relation to the supply of goods or services or both includes the monetary value of an act of forbearance. Therefore such a toleration of an act or a situation under an agreement constitutes supply of service and the consideration or monetary value of such toleration is exigible to tax.
Please become a Premium member. If you are already a Premium member, login here to access the full content.