N.M.D.C. Vs Authority For Advance Ruling (Karnataka High Court)
It is provided categorically under the CGST Act that no delay can be condoned after expiry of 30 + 30 days period. No such contingency was involved in the aforesaid case. Not only this, the doctrine of merger is not applicable in the facts and circumstances of the case. Hence, no relief can be granted on the basis of the aforesaid judgment.
No outer limit in respect of limitation was provided under the statute as provided under the CGST Act. There cannot be condonation of delay beyond the period of 60 days. Keeping in view the facts and circumstances of the case as doctrine of merger is not at all applicable. Hence, the judgment relied upon is again is of no help to the petitioner.
The provisions under the CGST Act, 2017 provides that the delay cannot be condoned beyond the period of 60 days.
The AAR was justified in rejecting the appeal on the ground of limitation as it was not having power to condone the delay beyond 30 days. Therefore, this Court also does not find reason to condone the delay keeping in view the statutory provisions.
The law of limitation is found upon maxims such as “Interest Reipublicae Ut Sit Finis Litium” which means that litigation must come to an end in the interest of society as a whole, and “vigilantibus non dormientibus Jura subveniunt” which means that the law assists those that are vigilant with their rights, and not those that sleep thereupon. The law of limitation in India identifies the need for limiting litigation by striking a balance between the interests of the state and the litigant.