In re Jaipur Metro Rail Corporation Limited (GST AAR Rajasthan)
Introduction: The case of Jaipur Metro Rail Corporation Limited (JMRC) delves into the complexities of assessing the GST impact on pre-GST lump sum contracts. With significant contractual obligations and tax adjustments, this case offers valuable insights into navigating GST implications.
Detailed Analysis:
1. Contractual Background: JMRC entered into an agreement with Continental Engineering Corp (CEC) for the construction of tunnels and metro stations in Jaipur. The contract, signed before the GST era, included taxes like VAT but excluded GST.
2. Contractual Adjustments: Clause 13.7 of the agreement allowed for adjustments in contract price due to changes in laws, implying potential adjustments for GST implementation. However, disagreements arose regarding the computation of GST liability post-GST.
3. Conflicting Views: The computation of GST liability and reimbursement between JMRC and CEC led to disagreements. JMRC’s proposal for reimbursement based on presumptions regarding service tax components faced opposition from CEC, leading to a conflict in interpretations.
4. Legal Interpretations: The jurisdictional officer provided insights on assessing the net impact of GST on pre-GST lump sum contracts. However, the conflict between JMRC and CEC extended beyond legal interpretations, focusing on contractual obligations and adjustments.
5. Advance Ruling Rejection: Despite the intricacies, the Advance Ruling application was deemed not maintainable under Section 98(2) of the GST Act, 2017. The ruling rejected the application, emphasizing the need for resolution within contractual terms rather than through Advance Ruling.
Conclusion: The Jaipur Metro case sheds light on the challenges of transitioning from pre-GST contractual agreements to the GST regime. With contractual adjustments, disagreements, and legal interpretations, it underscores the importance of clarity and agreement between parties. While seeking Advance Ruling provides insights, contractual clauses remain pivotal in resolving disputes arising from tax implications.
FULL TEXT OF THE ORDER OF AUTHORITY FOR ADVANCE RULING, RAJASTHAN
Note 1: Under Section 100 of the CGST/RGST Act, 2017, an appeal against this ruling lies before the Appellate Authority for Advance Ruling constituted under section 99 of CGST/RGST Act, 2017, within a period of 30 days from the date of service of this order.
Note 2:At the outset, we would like to make it clear that the provisions of both the CGST Act and the RGST Act are the same except for certain provisions. Therefore, unless a mention is specifically made to such dissimilar provisions, a reference to the CGST Act would also mean a reference to the same provision under the RGST Act. Further to the earlier, henceforth for the purposes of this Advance Ruling, a reference to such a similar provision under the CGST Act / RGST Act would be mentioned as being under the “GST Act”.
A. SUBMISSION OF THE APPLICANT(in brief):-
M/s Jaipur Metro Rail Corporation Ltd. (“JMRC” in short) awarded the contract to M/s. Continental Engineering Corp (“CEC” in short) for the Designing and Construction of Tunnel between Chand Pole and Badi Chaupar and reversal line by Shield TBM, Underground Metro Stations at Choti Chaupar& Badi Chaupar by Cut & Cover Method on East-West Corridor at Jaipur Metro (Phase 1B) at Jaipur, Rajasthan on 5th Oct., 2013.
In this agreement the amount quoted was lump sum including all taxes except VAT, the then tax instead of GST, because the VAT was exempt for the JMRC Project vide Notification issued on 06.10.2010 by Rajasthan Government. The Contractor was supposed to pay all taxes, duties and fees required to be paid by him under the prevailing statutes contract and the contract price was not to be adjusted for any of these costs except as stated in sub clause 13.7(Adjustment for change in Law) of General Condition Clause (GCC) of agreement.
Under pre-GST regime, “Works Contract” has been defined in Section 65B of the Finance Act, 1994 as a contract wherein transfer of property in goods involved in the execution of such contract is leviable to tax as sale of goods and such contract is for the purpose of carrying out construction, erection, commissioning, installation, completion, fitting out, repair, maintenance, renovation, alteration of any movable or immovable property or for carrying out any other similar activity or a part thereof in relation to such property. Hence, the contract between the employer and the contractor above was covered under the ambit of “Works Contract”.
Though, “Services by way of construction, erection, commissioning, or installation of original works pertaining to an airport, port or railways, including monorail or metro” was notified to be exempt from the payment to Service Tax vide Notification No. 25/2012-ST dated 20.06.2012. It is pertinent to notice that these services will not include a service used for providing such service. Notification No. 25/2012-ST dated 20.06.2012 was substituted by the Notification 09/2016-ST which excluded the monorail and metro from the ambit of the exemption. But there was an exception for the services by way of construction, erection, commissioning or installation of original works pertaining to monorail or metro, where contracts were entered before 1st March 2016, on which appropriate stamp duty, was paid, shall remain exempt. CBEC Circular No. 138/7/2011-ST dated 6 May 2011 opined that every service has to be classified and taxed in terms of its specific description and not in terms of a more general description. Clarification was further sought as to the taxability of works contract service (WCS) provided by subcontractors for dams, tunnels, etc. which was exempted and for which the contract was awarded to the main contractor. The CBEC clarified that: “in case the services provided by the sub-contractors to the main contractor are independently classifiable under WCS, then they too will get the benefit of exemption so long as they are in relation to the infrastructure project’s mentioned above. Thus, it may happen that the main infrastructure projects of execution of works contract in respect of roads, airports, railways, transport terminals, bridges tunnel and dams, is sub-divided into several sub-projects and each such sub-project is assigned by the main contractor to the various sub-contractors. In such cases, if the sub-contractors are providing works contract service to the main contractor for completion of the main contract, then service tax is obviously not leviable on the works contract service provided by such sub-contractor.” Hence, the above clarifications issued by the CBEC make it clear that there are two categories of sub-contractors for works contract services: (i) those to whom the support services are outsourced and (ii) those to whom part of the main work is outsourced. Work done by (ii) is treated as work of the same nature as the service of the main contractor and the same exemption is available for such work. On the other hand, subcontractors of category (i) provide services that are different in their nature, and these are treated differently. They are, at best, input services for the main works contract service.
As per Contract between CEC and JMRC, the payments are made in close regard to the contract price and the fluctuations that arise are taken into consideration, in a price variation (P.V) bill. Moreover, the Clause 13.7 also states that “The contract price shall be adjusted to take account of any increase or decrease in cost resulting from a change in the laws of the country (including the introduction of new Laws and the repeal or modification of existing Laws) or in the judicial or official government interpretation of such Laws, made after the Base Date, which affect the contractor in the performance of obligations under the Contract.” Hence, the introduction of GST is covered under the ambit of change in legislation or implementation of any law. Also, there is an understanding that the Contract price quoted by the CEC includes all cost including the taxes as well. Precisely, it included the taxes like excise duty, custom duty, service tax (the part that should be paid to the ancillary services obtained by the CEC and are not covered under the ambit of exemption) etcetera. Moreover, if there is any increase in the price due to the implementation of the new law, the extra burden to be borne by the JMRC.
B. INTERPRETATION AND UNDERSTANDING OF APPLICANT ON QUESTION RAISED (IN BRIEF):-
With the implementation of the GST laws, the exemption was withdrawn for the “Services by way of contraction, commissioning,
or installation of original works pertaining to Metro”, the contractor requested to adjust the contract price due to increase in the cost as the GST was applicable on those services at 18%, which was subsequently reduced to 12%.
Under the GST Regime, “Works Contracts” has been defined in Section 2(119) of the CGST Act, 2017 as “Works Contract” means a contract for building, construction, fabrication, completion, erection, installation, fitting out, improvement, modification, repair, maintenance, renovation, alteration or commissioning of any immovable property wherein transfer of property in goods (whether as goods or in some other form) is involved in the execution of such contract.“
As per Para 6(a) of Schedule 11 to the CGST Act, 2017, Works Contracts, as defined in Section 2(119) of the CGST Act, 2017, shall be treated as a supply of services.
Composite supply of works contracts, as defined in clause (119) of Section 2 of the Central Goods and Services Tax Act, 2017, supplied by way of construction, erection, commissioning, or installation of original works pertaining to metro is liable to the slab of 12% (6% COST and 6% SGST).
State Government exempts from the payment of tax payable on purchases of taxable goods and equipment mentioned in annexure -“A” of the notification, made by registered dealer for exclusive use of in execution of Work Contact for Jaipur Metro Rail Project. As per the contact agreement, Value Added Tax (VAT) and Rajasthan State Entry Tax were exempted.
As per Section 15(1) of CGST Act, 2017, the VAT paid was adjusted, and accordingly the value of supply was to be determined.
In this matter, JMRC started making payment of GST by deducting the amount of VAT payable by the CEC (other Party), adjustment of the Central Taxes, CST etc. as per the prevailing laws of the period on the date the agreement was executed, because the amount of taxes included in the cost of the works as per the agreement was kept the duty / liability of the CEC only.
The Service Tax portion was part of the Agreement, to be paid by the CEC itself, and accordingly, the same was presumed to be 40% of the works executed in the bill, and the same was not paid extra, being exempted and not to be included in the Contract Price.
Keeping the same in mind, the following proposal was submitted by JMRC regarding the computation of the additional GST liability to be borne by JMRC:





