Case Law Details
Case Name : Vrajesh Hirjee Vs Skyline Construction Co. (RNA Exotica) (Maharashtra RERA)
Related Assessment Year :
Courts :
RERA
Become a Premium member to Download.
If you are already a Premium member, Login here to access.
Sponsored
Vrajesh Hirjee Vs Skyline Construction Co. (RNA Exotica) (Maharashtra RERA)
The respondents have mentioned various reasons in their reply which caused delay in completing the project. Even if it is taken for granted that they are the genuine reasons which are beyond the control of the respondents, the respondents cannot claim the extension of more than six months of the date of possession in view of Section 8 (b) of Maharashtra Ownership Flats Act. Hence, the respondents are liable to refund the complainants