In re M/s. R.B. Construction Company (AAR Gujarat)
A. Does the work executed and invoice to be raised for the pending event of testing and commissioning by the applicant after the implementation of the Goods and Services Tax Act amount to supply, and specifically supply of works contract ?
The work of laying of underground pipeline network falls under the definition of “works contract” provided under Section 2(119) under the CGST Act, 2017 and the GGST Act, 2017. In respect of that part of supply wherein time of supply is on or after the appointed date, Goods and Services Tax is required to be paid.
B. Is the applicant entitled to enjoy proportionate credit worth 10% duty of excise and VAT paid on materials bought vide invoices showing Excise and VAT separately, under the transition provisions so that there is no double taxation i.e. levy of tax on tax is avoided ?
The applicant is not entitled under Section 140(6) of the CGST Act, 2017 and the GGST Act, 2017 to avail input tax credit.
FULL TEXT OF ADVANCE RULING
The applicant submitted that they had bid in a tender issued by the Rajkot Municipal Corporation (RMC) to supply pipes, lay the pipes in desired formation as planned by the Government and to test the pipes against the leakages and then commission the project. The work to be executed as per the tender was to construct a pipeline network as per the specifications and design of the RMC. The release of the payment of the applicant fixed by the RMC is as follows :-