In re Sevak Ram Sahu (M/s. S.R.S. Enterprises) (GST AAR Rajasthan)
Services of pure labour contract supplied by way of construction, erection, commissioning, installation, completion, fitting out, repair, maintenance, renovation, or alteration of a civil structure or any other original works under PMAY is exempted from GST vide Entry 10 of the Notification No. 12/2017-Central Tax (Rate) dated 28.06.2017 (as amended).
FULL TEXT OF ORDER OF AUTHORITY OF ADVANCE RULING, RAJASTHAN
Note: Under Section 100 of the CGST/RGST Act, 2017, an appeal against this ruling lies before the Appellate Authority for Advance Ruling constituted under section 99 of CGST/RGST Act, 2017, within a period of 30 days from the date of service of this order.
- At the outset, we would like to make it clear that the provisions of both the CGST Act and the RGST Act are the same except for certain provisions. Therefore, unless a mention is specifically made to such dissimilar provisions, a reference to the CGST Act would also mean a reference to the same provision under the RGST Act. Further to the earlier, henceforth for the purposes of this Advance Ruling, a reference to such a similar provision under the CGST Act / RGST Act would be mentioned as being under the “GST Act”.
- The issue raised by SEVK RAM SAHU, (M/s S.R.S. Enterprises), 172, Hasanpura C, Khatipura Road, Jaipur, Rajasthan 302006(hereinafter the applicant) is fit to pronounce advance ruling as it falls under the ambit of the Section 97(2) (b)given as under: –
b. Applicability of a notification issued under the provisions of this act;