Advertisement
Advertisement
Skip to content
Follow Us on
Advertisement
TOP STORIES
Income Tax

Closing WIP Cannot Be Recomputed Ignoring Prior Revenue Recognition: ITAT Hyderabad

Case Law Details

TaxGuru Citation
2026 taxguru.in 19762
Case Name
Krishna Infra Vs ACIT (ITAT Hyderabad)
Appeal Number
Premium Access
Date of Judgement/Order
Premium Access
Related Assessment Year
2015-16
Subscribe to download.

Already Upgraded? Log in.

Advertisement

Krishna Infra Vs ACIT (ITAT Hyderabad)

Closing Work-in-Progress Cannot Be Recomputed Solely on the Cost-Incurred Ratio Where Prior Revenue Recognition Is Ignored: ITAT Hyderabad

Hyderabad ITAT deletes ₹3.76 crore addition and remands the land advance issue

In Sri Krishna Infra v. ACIT, Circle 2(1), Tirupati, ITA No. 368/HYD/2026, decided on 20 November 2026 for AY 2015–16, the Hyderabad ITAT deleted an addition of ₹3,75,56,279 for alleged understatement of closing work-in-progress. The Assessing Officer had recomputed the value under the percentage completion method by comparing cumulative expenditure with estimated project cost, without accounting for revenue already recognised in earlier years. The Tribunal separately restored a ₹2.50 crore addition under Section 69 to the Assessing Officer for the limited purpose of verifying the cash book and the source of a land advance.

How the work-in-progress difference arose

The assessee, a firm engaged in constructing residential apartments, filed its return declaring taxable income of ₹55,20,847. A survey under Section 133A on 10 September 2015 resulted in the impounding of books and other documents. During scrutiny, the Assessing Officer called for the firm’s calculation of closing work-in-progress as on 31 March 2015.

The firm reported closing work-in-progress of approximately ₹6.95 crore, applying a 30% stage of completion and taking into account the estimated cost, revenue recognised in the preceding two financial years and the remaining cost attributable to the unsold area. The Assessing Officer divided cumulative expenditure of approximately ₹16.16 crore by the total estimated project cost of ₹34.97 crore to arrive at a completion rate of 46.21%. Applying that rate to the ₹23.17 crore estimated cost attributable to the unsold area, he determined closing work-in-progress at ₹10,70,62,040. The CIT(A) upheld the resulting addition.

Prior years’ revenue mattered to the valuation

The Tribunal noted that both sides proceeded on the percentage completion method and that the actual expenditure and estimated project cost were undisputed. The difference lay in how the completion percentage and the closing value were determined. Referring to Accounting Standard 7 (AS-7), the Bench explained that the closing valuation must be examined in the context of total project revenue, estimated project cost, actual expenditure to date, revenue already recognised and the project’s profit or loss.

The Tribunal found no error in the firm’s working on the facts before it. The Assessing Officer’s calculation substituted a cost-based percentage without accounting for revenue recognised in the preceding two years. The Bench also observed that one year’s closing work-in-progress becomes the next year’s opening work-in-progress. An increase in the closing value raises profit in the current year and, through the corresponding opening value, reduces profit in the following year. The Tribunal treated that timing effect as an additional consideration and deleted the ₹3,75,56,279 addition.

Cash book showed funds for the ₹2.50 crore advance

The survey also revealed that the firm had paid a cash advance towards a land purchase in two instalments, ₹2 crore on 7 December 2014 and ₹50 lakh on 25 December 2014. The firm said the agreement was cancelled and the advance refunded in the same financial year. The Assessing Officer maintained that the relevant cash book had not been furnished to establish the source on the payment dates. He added the amount under Section 69, and the CIT(A) sustained it.

The cash-book extracts produced before the Tribunal recorded both payments. They showed a cash balance of ₹2,01,47,786 on the date of the first payment and linked the second payment to bank withdrawals on 8 and 24 December 2014. The firm maintained that the books had been impounded during the survey and were available to the officer. Given the conflicting accounts about whether the cash book had been available for examination, the Tribunal ordered limited verification by the Assessing Officer, with a direction to delete the addition if the source is established. The appeal was partly allowed.

Author’s comments

The work-in-progress ruling is best read in the context of the specific computation used by the Assessing Officer. The Bench objected to applying the revised percentage to the estimated cost of the unsold area without reconciling the revenue already recognised. A project-wise working that carries forward the prior years’ recognised revenue and costs helps test whether a proposed adjustment correctly measures current-year income. The corresponding opening balance in the next year shows the timing effect of any valuation change.

On the land advance, the same-year cancellation and refund explained how the transaction ended. The source inquiry concerned how it began, specifically whether the firm had sufficient recorded cash on each payment date. The Tribunal’s direction makes the outcome turn on that verification. The distinction between the two outcomes is important: the work-in-progress addition was deleted outright, while deletion of the Section 69 addition depends on the Assessing Officer verifying the cash-book entries and the stated sources.

FULL TEXT OF THE ORDER OF ITAT HYDERABAD

This appeal filed by the assessee is directed against the order of the learned Commissioner of Income Tax (Appeals), National Faceless Appeal Centre [in short “NFAC”], Delhi, dated 22.12.2025, pertaining to the assessment year 2015-16.

2. The grounds raised by the assessee read as under :

“1. The order of the Appellate Commissioner is contrary to law, circumstances of the case.

2. The Appellate Commissioner erred in confirming the order of the facts and Assessing Officer, who had calculated the closing work in progress on total cost of construction as on 31.03.2015 without deducting the sale price off flats which have been already sold during the year ending 31.03.2015.

3. The Appellate Commissioner erred in confirming the order of the Assessing Officer, who had computed the closing work in progress as on 31.03.2015 as Rs. 10,70,62,040/-, instead of and thus adding an amount of Rs. 3,75,56,279/-.

4. The Appellate Commissioner, erred in confirming the order of the A.O, who had treated the amount given for purchase of land, which were part of the books of account of the firm, as unexplained income and making an addition u/s. 69 of the Income Tax Act amounting to Rs.2,50,00,000/-.

5. Any other grounds which the assessee may urge either before or at the time during the hearing.”

3. The brief facts of the case are that, the assessee is a firm engaged in the business of construction of residential apartments filed its return of income for the assessment year 2015-16 on 28.03.2016 admitting total taxable income of Rs.55,20,847/-. A survey under Section 133A of the Income Tax Act, 1961 was conducted in the case of the assessee on 10.09.2015, and during the course of survey, books of accounts and other documents were impounded. Further, during the course of survey, it was ascertained that, the assessee firm has to offer an income of Rs.2,56,26,990/- for the year under consideration. Further, an amount of Rs.2,50,00,000/- was found to have been invested by the assessee firm for purchase of land and the source of which was unexplained and the payment has also been made in cash.

4. The case was selected for scrutiny and during the course of scrutiny proceedings, the Assessing Officer called upon the assessee to produce relevant details, including financial statements, books of accounts, etc. In response, the assessee appeared from time to time and filed relevant details along with books of accounts. During the course of assessment proceedings, the Assessing Officer, to verify the correctness of the valuation of closing stock adopted by the assessee, called upon the assessee to file relevant details of valuation of closing stock. In response, the assessee submitted that, it was in the business of construction of residential apartments following percentage completion method for recognizing revenue and work in progress and based on relevant project cost and revenue recognized up to the financial year under consideration has worked out closing work in progress of Rs.6,95,05,761/-. The assessee had also filed calculation of closing work in progress with supporting evidences. The A.O. after considering relevant submissions of the assessee observed that, closing work in progress reported by the assessee is not in accordance with percentage completion method, and therefore by taking the total cost incurred for the financial year 2012-13 to financial year 2014-15, which was at Rs.16,16,33,502/-, worked out percentage completion of project by taking into account total estimated cost of project at Rs.34.97 crores and arrived at 46.21 percentage completion of the project. Since the assessee has considered 30% completion of the project, the A.O. has determined closing value of work in progress by taking into account the cost for balance unsold area as on 31.03.2015 for Rs.23.17 crores and arrived at closing work in progress as on 31.03.2015 at Rs.10,70,62,040/-. Since the assessee has reported closing work in progress of Rs.6,95,05,761/-, the difference amount of Rs.3,75,56,279/- has been treated as under-valuation of closing stock and added to the total income.

5. The A.O. further noted that, the assessee had made cash payment of Rs.2,50,00,000/- for purchase of property, and to examine this issue, called upon the assessee to file relevant details, including copy of agreement, if any, cash book for evidencing payment of cash and its source. In response, the assessee submitted that, the firm has purchased a land for Rs.2.5 crores and also paid advance on two occasions in cash and the same has been recorded in the books of accounts. Since the transaction did not materialized, subsequently, a cancellation deed was executed and advance paid by the assessee was refunded. The A.O. after considering the relevant submissions of the assessee and also taking note of findings recorded in the survey proceedings, observed that, although the assessee has paid cash advance of Rs.2 crores on 07.12.2014 and Rs.50 lakhs on 25.12.2014, but failed to explain the source by filing relevant cash book to prove the availability of cash at the time of making the payment. Although the transaction was cancelled within the same financial year, but fact remains that whether the assessee was having sufficient cash in hand at the time of making payment or not has to be ascertained and in absence of relevant cash book submitted by the assessee, it is difficult to ascertain the availability of source. Therefore, the A.O. rejected assessee’s submission and made addition of Rs.2.5 crores under Section 69 of the Income Tax Act, 1961.

6. Aggrieved by the assessment order, the assessee preferred an appeal before the Ld. CIT(A). Before the Ld. CIT(A), the assessee reiterated its submissions made before the A.O. and argued that the A.O. was erred in computing closing work in progress of Rs.10.70 crores as against closing work in progress reported by the assessee for Rs.6.95 crores without considering relevant AS-7 which provides for the method for valuation of work in progress in case of construction contracts. The assessee further submitted that, assuming for a moment, there is an under-valuation of closing stock as on 31.03.2015, but fact remains that the closing stock of 31.03.2015 becomes opening stock of subsequent year and in case any suppression of profit for the year under consideration, the same will be offset by reductions in the subsequent assessment years as a tax-neutral, and therefore, the closing work in progress determined by the A.O. is contrary to the submission of the assessee and thus, additions made by the A.O. should be deleted. The assessee had also explained cash payment of Rs.2.5 crores for purchase of property and cancellation of agreement and received back the advance paid for purchase of property and claimed that the books of accounts were impounded by the department during the course of survey, and therefore, the conclusion drawn by the A.O. that assessee has not submitted cash book to ascertain cash payment is incorrect. Since the assessee has recorded cash payment and cash receipts and both events have happened in the same financial year, the A.O. was erred in making additions under Section 69 of the Act.

7. The Ld. CIT(A) after considering submissions of the assessee and also taking note of various reasons given by the A.O. for making additions towards suppression of work in progress, rejected submission of the assessee and sustained additions made by the A.O. on the ground that, going by the total estimated project cost and cost incurred by the assessee, there is no dispute about 46.21 percent completion in the project as on 31.03.2015 and if we go by the percentage of completion, then the percentage adopted by the assessee is incorrect, and therefore, the A.O. was rightly worked out closing work in progress at Rs.10.7 crores as against closing work in progress reported by the assessee for Rs.6.95 crores. Since, there is a difference between closing work in progress worked out by the A.O. and reported by the assessee, the A.O. was right in making additions of Rs.3,75,56,279/- towards suppression closing work in progress.

8. The Ld. CIT(A) has also sustained additions made by the A.O. towards unexplained investment in purchase of property for Rs.2.5 crores by holding that although, the assessee claims to have paid advance in cash and received back the same by cash in the same financial year, but fact remains that the assessee has failed to file relevant cash book in order to explain source at the time of making payment of Rs.2.5 crores in cash. The subsequent reversal of the transaction within the same financial year does not absolve the assessee of the statutory obligation to explain the source of the investment at the time it was made. In absence of satisfactory explanation supported by evidences, the conditions prescribed for making addition u/s 69 of the Act, stands fulfilled, and thus, the A.O. was justified in treating the sum of Rs.2.50 crores as unexplained investment.

9. Aggrieved by the order of Ld. CIT(A), the assessee is now in appeal before the Tribunal.

10. The first issue that came up for our consideration from ground nos. 2 and 3 of the assessee’s appeal is addition towards difference in closing work-in-progress of Rs. 3,75,56,279/-.

11. The learned counsel for the assessee, Shri A. Srinivas, C.A. submitted that, the AO was erred in making additions towards suppression of closing stock by estimating closing work-in-progress at Rs. 10.70 crores, as against closing work-in-progress reported by the assessee for Rs. 6.95 crores. The learned counsel for the assessee submitted that, there is no dispute about method of valuation for closing stock followed by the assessee, and in fact the assessee follows percentage completion method as prescribed under AS-7 issued by the ICAI. The assessee had also considered the estimated project cost, actual expenditure incurred up to the date, revenue recognized for last two financial years to arrive at closing work-in-progress of Rs. 6.95 crores, whereas the AO has determined closing work-in-progress of Rs. 10.70 crores by taking into account only actual expenditure incurred by the assessee and compared with estimated project cost to arrive at percentage of completion of the project without considering revenue recognized by the assessee for the last two financial years and from the above, it is very clear that, the AO has not followed AS-7 for arriving at closing work-in-progress. Further, assuming for a moment, the AO was correct in determining closing work-in-progress at Rs.10.7 crores, the fact remains that the closing work-in-progress of this year becomes opening work in progress of subsequent years, and to that extent there may be reduction of profit for the year under consideration, but the said reduction will offset due to reduction of profit in the subsequent years and becomes tax-neutral exercise. Since the AO has worked out closing work in progress without considering the percentage completion method, the additions made by the A.O. and sustained by the Ld. CIT(A) cannot be upheld. Therefore, he submitted that, the additions made by the A.O. should be deleted.

12. The Ld. CIT-DR, Ms. U. Mini Chandran, on the other hand, supporting the order of the Ld. CIT(A) submitted that, when assessee is following percentage completion method, he should work out closing work-in-progress in terms of AS-7 and if we follow AS-7, the closing work-in-progress reported by the assessee is incorrect, because the assessee has considered 30% project completion up to the date of balance sheet by taking into account cost of balance unsold area and same is not in accordance with method prescribed for valuation of closing stock. Since there is a clear difference between work in progress of the assessee and actual work in progress worked out by the AO in terms of AS-7, the Ld. CIT(A) has a right to sustaining additions made by the AO. Therefore, she submitted that, the order of the AO and Ld. CIT(A) should be upheld.

13. We have heard both parties, perused the material available on record and had gone through the orders of the authorities below. There is no dispute with regard to the fact that the appellant firm was engaged in the business of construction contracts, i.e., construction of residential apartments, and is following percentage completion method for the recognition of revenue as well as work in progress. The assessee has reported closing work-in-progress of Rs. 6.95 crores, whereas the AO has ascertained closing work-in-progress of Rs. 10.70 crores. There is no dispute about facts including actual amount of expenditure incurred by the assessee up to the end of financial year 2014-15 and the estimated cost of the project considered by the assessee and the AO. The only difference is about percentage of completion of the project worked out by the assessee in the year. The assessee has worked out 30% completion of the project by taking into account estimated cost of the project at Rs. 34.97 crores and by taking into account total saleable area and balance unsold area as on 31/3/2015, has worked out total estimated cost of remaining unsold area at Rs. 23.17 crores and since the project was completed at 30%, has worked out closing work-in-progress of Rs. 6,95,07,860/-. On the other hand, the A.O. has worked out the percentage of completion of the project at 46.21% by taking into account the actual expenditure incurred by the assessee up to 31.03.2015 and considering the total estimated cost of the project, as against 30% completion worked out by the assessee. Further, taking into account the 46.21% completion, the A.O. has worked out the closing work-in-progress at Rs.10.70 crores on the remaining cost of the unsold area of Rs.23.17 crores.

14. We have given our thoughtful consideration to the reasons given by the A.O. in light of various arguments of the assessee and we find that, the work-in-progress arrived at by the AO is incorrect going by the percentage completion method provided under AS-7 issued by the ICAI, because as per the percentage completion method, the closing work-in-progress can be determined by taking into account total project revenue, estimated cost of the project, actual expenditure incurred up to the balance sheet date, actual revenue recognized by the assessee for last financial years, and profit or loss, if any, arrived at by the assessee from the project. In the present case, the assessee has considered the closing work-in-progress of Rs. 6.95 crores by taking into account total estimated project cost, revenue recognized for last two financial years and the remaining cost of unsold saleable area, whereas the A.O. has directly worked out the percentage of completion of the project by comparing the actual cost incurred by the assessee with the total estimated project cost, which, according to us, is not the correct method for determining the percentage of completion of the project. Since there is no error in the method followed by the assessee for determining the closing work-in-progress, in our considered view, the method followed by the AO for determining closing work-in-progress at Rs.10.70 crores cannot be upheld.

15. Be that as it may. Assuming for a moment, there is a difference between work-in-progress reported by the assessee and actual work-in-progress determined by the AO and the same needs to be considered as income for the year under consideration, but fact remains that the closing work-in-progress of the current year becomes opening work-in-progress of the subsequent financial years and underreporting of profit for the year under consideration will be offset from reduction in profit for the subsequent year, because of increase in value of opening stock and becomes tax neutrality in the subsequent financial year and therefore, on this count also, without any correct procedure followed by the AO, estimating closing work in progress by taking incorrect figures cannot be upheld.

16. In this view of the matter and considering facts and circumstances, we are of the considered view that, the A.O. erred in making addition of Rs. 3,75,56,279/- towards suppressed value of closing work in progress. The Ld. CIT(A) without appreciating relevant facts upheld the additions made by the AO. Thus, we set aside the order of the Ld. CIT(A) on this issue and delete addition made by the AO towards difference in value of closing work in progress of Rs. 3,75,56,279/-.

17. The next issue that came for consideration from ground no.4 of assessee’s appeal is addition of Rs.2.5 crores as unexplained investment u/s 69 of the Act, towards alleged cash payment for purchase of property.

18. The learned counsel for the assessee submitted that, the assessee has entered into an agreement for purchase of property and has paid Rs. 2.5 crores advance on two dates, and such advance has been paid in cash. The assessee has also cancelled the agreement due to various reasons, and advance paid by the assessee has been refunded in the same financial year. The advance paid by the assessee has been recorded in the cash book, and advance received by the assessee has also been recorded in the cash book. Since the advance payment for purchase of land was part of regular books of accounts of the assessee and source for the said payment has been explained, the Assessing Officer cannot invoke provisions of Section 69, because the provisions of Section 69 is applicable only in a case where the assessee has made investment, which is not recorded in the books of accounts if any, maintained by him, and the assessee offers no explanation about the nature and source of the investment. Since the assessee has recorded investment in the books of accounts, the Assessing Officer erred in making additions under Section 69 of the Act. Therefore, he submitted that the additions made by the Assessing Officer should be deleted.

19. The Ld. CIT-DR supporting the order of the Ld. CIT(A) submitted that, there is no dispute about the fact that during the course of survey, documents were found which shows advance payment of Rs. 2.5 crores for purchase of property. The assessee has failed to explain the source for the said payment. Although the assessee claims to have recorded the investment in the books of accounts and further claimed that the agreement was subsequently cancelled and advance paid by the assessee was refunded by the sellers, but fact remains that the assessee has not furnished any cash book to the Assessing Officer for verification to ascertain the availability of cash as on the date of payment. In absence of any evidences, the Assessing Officer rightly made additions towards cash payment under Section 69 of the Act, and the Ld. CIT(A) after considering relevant facts, has rightly sustained additions made by the Assessing Officer. Therefore, she submitted that, the additions made by the Assessing Officer and sustained by the Ld. CIT(A) should be upheld.

20. We have heard both the parties, perused the material available on record and had gone through orders of the authorities below. There is no dispute about the fact that during the course of survey under Section 133A of the Act, it was noticed that, the assessee firm has paid sum of Rs. 2.5 crores advance for purchase of property in cash, and the source for the said investment claiming to have not explained. The Assessing Officer made additions towards advance payment under Section 69 of the Act, on the ground that although the assessee claims to have cancelled the agreement and received back the advance, but failed to file relevant cash book to explain source for cash payment on 07.12.2014 and 25.12.2014. It was the arguments of the counsel for the assessee that, the transaction of payment of advance and subsequent cancellation of advance had also happened in the same financial year and the assessee has paid advance of Rs. 2.5 crores out of advance received from the customers for sale of flats and the same has been recorded in the books of accounts. The assessee further claimed that, since the agreement was cancelled, the assessee has received back the advance paid by the assessee, and the part of the amount has been deposited into bank account.

21. We have gone through relevant arguments of the counsel for the assessee and counter arguments of the Ld. CIT-DR on this issue, and after considering relevant arguments, we find that, the assessee has furnished relevant extract of cash book for the year under consideration, and as per the cash book maintained by the assessee, cash payment of Rs.2 crores on 07.12.2014 was recorded in the cash book, and as on the date of payment, the assessee was having sufficient cash balance of Rs. 2,01,47,786/- Further, the assessee had also paid sum of Rs. 50 lakhs as on 25.12.2014, and the same has been recorded in the cash book, and the source for the said payment was out of cash withdrawn from bank on 08.12.2014 and 24.12.2014. From the cash book filed by the assessee, it seems that cash payment of Rs. 2.5 crores was recorded in the books of accounts i.e., cash book, and as on the date of payment, the assessee was having sufficient cash balance. Since the assessee has recorded the investment in the books of accounts and source for the said investment has been explained, in our considered view, the additions made by the Assessing Officer under Section 69 of the Act, is incorrect and needs to be deleted. However, fact remains that there were contradictory arguments on the issue from the Assessing Officer and the assessee, where, the Assessing Officer claims that the assessee has not furnished any cash book to support the arguments of payment of cash advance with known source of income, whereas the assessee claims that the books of accounts were impounded by the department during the course of survey, and the same was available with Assessing Officer. Since there are divergent views on the issue of production of cash book for verification, and further as per the cash books furnished by the assessee before the Tribunal, there is sufficient cash balance at the time of making advance payment of Rs. 2.5 crores for purchase of property, in our considered view, for the limited purpose of verification of the cash book, the issue needs to be set aside to the file of the Assessing Officer. Thus, we set aside the order of Ld. CIT(A) on this issue and restore the issue back to the file of the Assessing Officer. The Assessing Officer is directed to verify the cash book submitted by the assessee, and in case, the assessee is able to explain the source, then the Assessing Officer is directed to delete additions made towards advance payment for purchase of property under Section 69 of the Income Tax Act.

22. In the result, the appeal of the assessee is partly allowed.

Order pronounced in the Open Court on 20th November, 2026.

Advertisement

Author Info

CA Vijayakumar Shetty
Qualification: CA in Practice
Company: Shetty & Co, Chartered Accountants, Mangalore
Location: Mangalore, Karnataka
Articles Published: 7,967

Join TaxGuru's Network for the latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.