Sl No | Provision of the RERA Act | Details | Section |
1 | Prior Registration of Real Estate Project | Obtain the RERA registration on receipt of the Sanctioned plan (may be postponed if the intention is not to sell immediately) | Sec 3 / Sec 4 |
2 | First time Update / Post Registration | On registration of the Project | Sec 11 |
3 | Quarterly Updates | Within 15 days from the end of each Quarter | Sec 11 read with Rules |
4 | Annual Audit of Accounts | Within 6 months from the end of financial year | Sec 4(2)(L)(D) |
5 | Obtaining Professional Certificates –
a) Architect, b) Engineer, and c) Chartered Accountant |
Architect, Engineer, and Chartered Accountant in Practice certificates shall be obtained for each withdrawal of funds from the RERA Designated bank account. | Sec 4(2)(L)(D) |
6 | Reporting of Completion | On completion of 100% development (internal and development) works in the project. Report within the same quarter of completion |
Circular |
7 | Application for Extension of End date for the project | Within 3 months before the end date of registration | Sec 6 read with Rule |
8 | Modification Application | Prior / post-approval of the authority for any modification in the Registration Application depending on the modification/amendment. | Sec 14 |
9 | Formation of Association of Allottees | shall be formed within three months of the majority of allottees having booked the plot/apartment | Sec 11 |
10 | Transfer of Title | within three months from date of issue of occupancy certificate. | Sec 17 |
11 | Refund/Return of amount on Cancellation | Within 30/60 days of Such Cancellation | Sec 18 read with Rule |
12 | Conveyance of plot/apartment | Conveyance deed after receipt of Occupancy certificate | Sec 17 |
13 | Hand- over
a. the necessary documents b. plans c. including common areas to the association of the allottees |
within thirty days after obtaining the occupancy certificate | Sec 17 |
14 | Structural Defect warranty by the Promoter | Five years from the date of handing over to the allottee | Sec 14 |
15 | Attend to Structural Defect by the Promoter | Promoter to rectify such defects without further charge, within thirty days from the date of notice | Sec 14 |
16 | Grant of Registration by the authority for the real estate project | Within 30 days from the date of application | Sec 5 |
Auhtor is a Chartered Accountant and can be rachable on vinay@vnv.ca
Sponsored
Kindly Refer to
Privacy Policy &
Complete Terms of Use and Disclaimer.
Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.
One Comment
Cancel reply
What is RERA timetable and how to access it through RERA website ? Or else is it required to be obtained from developer only ? Kindly share your views.