Interim EMI Orders Require Verification of Loan Disbursement and Homebuyer Default

Case Law Details

TaxGuru Citation
2026 taxguru.in 19709
Case Name
Ravi Kumar Jangra and Anr. Vs Union of India & Ors. (Supreme Court of India)
Appeal Number
Premium Access
Date of Judgement/Order
Premium Access
Subscribe to download.

Already Upgraded? Log in.

Advertisement

Ravi Kumar Jangra and Anr. Vs Union of India & Ors. (Supreme Court of India)

Court Must Examine Loan Disbursement and Find Homebuyer Default Before Ordering Interim Instalment Payments

Supreme Court Protects Homebuyers Facing Bank Recovery

Can a court direct homebuyers to pay housing loan instalments at the interim stage when they allege that the bank released funds to the builder ahead of the agreed construction milestones? The Supreme Court held that the competent court must first examine whether the bank disbursed the loan strictly in accordance with the tripartite agreement and determine the nexus between the builder and the bank authorities. An interim direction to pay instalments requires a categorical finding that the homebuyers are in default.

The Court directed the Civil Court to refrain from taking coercive action against the petitioners or similarly placed homebuyers before deciding that issue. The protection was ad-interim, with the underlying contractual and insolvency issues left for the competent forums to decide.

Loan Disbursement Was Linked to Construction Progress

The petitioners booked homes in the Krishna Housing Scheme at Sector 14, Sohna, Gurugram, a project launched by Raheja Developers Limited. The homebuyers, State Bank of India and the developer entered into a tripartite agreement concerning the housing loans. Under the arrangement described in the order, disbursement was linked to the progress of construction.

The buyers alleged that the developer failed to honour its commitments and that SBI released funds to the developer without corresponding construction progress. The Supreme Court recorded the apparent mismatch between payment and progress. Whether the payments complied with the agreement remained a matter for the competent court to examine.

Meanwhile, the National Company Law Tribunal admitted the developer into the corporate insolvency resolution process on 21 August 2025. In those proceedings, the developer proposed to refund amounts deposited by homebuyers in six monthly instalments. While those proceedings were pending, SBI filed recovery suits against the petitioners before the Commercial Court at Saket, New Delhi. The court issued certain ad-interim directions regarding payment of instalments to SBI.

The Court Must Examine the Bank’s Conduct Before Finding Default

The Supreme Court placed the tripartite agreement at the centre of the interim inquiry. The agreement governed when the bank could release funds to the builder. Once the buyers questioned whether the releases matched the agreed construction progress, the court hearing the recovery suits had to examine how and when the bank disbursed the money. It also had to consider the relationship between the builder and the bank authorities in connection with those disbursements.

The sequence matters. The competent court must first examine the contractual conditions for disbursement and whether the releases complied with them. It must then determine whether the buyers were in default. Only after returning a categorical finding of default can it issue an interim direction requiring payment of instalments. The Supreme Court accordingly extended protection from coercive action to the petitioners and similarly placed homebuyers until the issue was decided.

Commercial Court May Revisit Its Existing Interim Directions

The Supreme Court expressly gave the Commercial Court liberty to modify its existing interim order or directions after hearing the parties. This allows the court hearing the recovery suits to consider the bank’s and the buyers’ evidence before deciding what interim relief is warranted. The relevant inquiry includes the terms governing release of the loan, the construction progress at the time of each disputed release and the basis on which SBI alleges default.

The Supreme Court disposed of the writ petition on those terms. It left the merits of the recovery suits and the issues pending before the NCLT or NCLAT to be decided in accordance with law. The developer’s proposed refund was part of the insolvency background recorded in the order. The direction protecting the homebuyers concerned coercive recovery pending the Commercial Court’s determination.

Author’s Comments

The ruling is significant for construction-linked housing loans because the bank’s claim of default must be examined against the terms under which it paid the developer. A loan statement can show when money was released and when instalments fell due. The tripartite agreement and evidence of construction progress answer a further question that matters here. They show whether the bank was entitled to make each disputed release when it did. That inquiry is especially important where the borrower received no corresponding progress on the home for which the money was released.

The immediate consequence is procedural. Before ordering interim instalment payments, the recovery court must hear the parties and make the required finding on default after examining the bank’s compliance with the agreement. The ultimate liability of the buyers and the treatment of their refund claims remain for the respective forums. The order gives homebuyers time-bound procedural protection in the sense that it lasts until the threshold issue is decided, while preserving the bank’s opportunity to establish its claim on the evidence.

FULL TEXT OF THE SUPREME COURT JUDGMENT/ORDER

1. The petitioners are home buyers in a project known as ‘Krishna Housing Scheme’, situated at Sector-14, Sohna, Gurugram. The project was launched by respondent No. 4, M/s Raheja Developers Limited private builder-cum-developer.

2. It appears that a Tripartite Agreement was executed between the petitioners, the State Bank of India and respondent No. 4 regarding housing loans availed by the petitioners. It is alleged that the builder-cum-developer failed to honor its commitment as per the Tripartite Agreement. Although, the disbursement of the loan was linked to construction progress, the Bank appears to have made payment to the builder without any corresponding progress in the construction. Meanwhile, respondent No. 4, builder-cum-developer was admitted into CIRP by the National Company Law Tribunal (for short, “NCLT”) on 21.08.2025. In CIRP proceedings, the builder-cum-developer had proposed to refund the amount deposited by home buyers in six monthly installments.

3. Pending above proceedings, the State Bank of India filed recovery suits against the Petitioner-home buyers before Commercial Court, Saket Courts, New Delhi. Consequently, certain ad-interim directions were issued by the Civil Court regarding payment of installments by the petitioners to the State Bank of India.

4. In our considered opinion, it is the bounden duty of the competent Court to first determine the nexus between the builder and the Bank authorities and examine whether the Bank disbursed the loan amount to the builder strictly in terms of the Tripartite Agreement. Unless a categorical finding is returned that the home buyers are in default, no interim direction regarding payment of installments can be issued against them. We, therefore, direct the Civil Court to not take any coercive action against the petitioners or similarly placed home buyers without first deciding the above-mentioned issue.

5. It is clarified that we have not expressed any opinion on merits of the case and only an ad-interim protection has been granted to the home buyers against coercive means. All the issues pending before the NCLT/NCLAT and/or the Commercial Court shall be decided notwithstanding the observations made hereinabove and in accordance with law. The Commercial Court shall be at liberty to modify the interim order/directions already issued by it after hearing the parties.

6. The Writ Petition stands disposed of, in the above terms.

7. Pending application(s), if any, shall stand closed.

Advertisement

Author Info

CA Vijayakumar Shetty
Qualification: CA in Practice
Company: Shetty & Co, Chartered Accountants, Mangalore
Location: Mangalore, Karnataka
Articles Published: 7,918

Join TaxGuru's Network for the latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.