Section 14 (3) of the Real Estate (Regulation and Development) Act, 2016 lays down that,“In case any structural defect or any other defect in workmanship, quality or provision of services or any other obligations of the promoter as per the agreement for sale relating to such development is brought to the notice of the promoter within a period of five years by the allottee from the date of handing over possession, it shall be the duty of the promoter to rectify such defects without further charge, within thirty days, and in the event of promoter’s failure to rectify such defects within such time, the aggrieved allottees shall be entitled to receive appropriate compensation in the manner as provided under this Act”.
One of the concerns in the real estate sector before this Act came into force was the quality of construction and sense of responsibility on the part of the builder/promoter towards the allottee. The builder/promoter was not bound by any Act or Regulations to check on the materials used for the construction and also quality of construction in a project building. The builder/promoter would not take any responsibility in rectifying the structural defects once the possession of the building was handed over to the allottee/s and allottee were forced to rectify the structural defects again by spending from his pocket, in spite of investing huge/heavy amount on the project building. There was no sense of security to the allottees in regard to the quality of construction on any project building constructed by the builder/promoter/s.
Section 14(3) of the Real Estate (Regulation and Development) Act, 2016, now eliminates the absence of professionalism in the real estate sector and makes it mandatory for promoter/developers to rectify any construction/structural defects that may be noticed, even after possession has been handed over to the allottee/buyer/investor for a period of five years and within thirty days after the structural defect coming into the knowledge/notice of the builder and thus, making the allottee feel secure on his investment on the project building.
WHAT ACCORDING TO THE ACT IS DEFECT LIABILITY/STRUCTURAL DEFECTS?
As the word “Defect Liability/Structural Defect” is not specifically defined in the Karnataka Real Estate (Regulation and Development) Rules, 2017, thus giving rise to confusion on the definition, we are referring to the Rules framed by other States on Real Estate Act, 2016 which have explicitly defined the word “Structural Defect”.
Telengana State Real Estate (Regulation and Development) Rules, 2017 defines “Defect Liability” in its Agreement of Sale as,
“Structural defect or any other defect in workmanship, quality or provision of services or any other obligations of the promoter as per the agreement for sale relating to such development is brought to the notice of the promoter within a period of five years by the allottee from the date of handing over possession, it shall be the duty of the promoter to rectify such defects within such time, the aggrieved allottees shall be entitled to receive appropriate compensation in the manner as provided under the Act”.
The Telengana Rules, 2017 further defines the word “Defect Liability” as;
Notwithstanding anything contained in the above clause the following exclusions are made:
-
- Equipment (lifts, generator, motors, STP, transformers, gym equipment etc.,) which carry manufacturer’s guarantees for a limited period.
- Fittings related to plumbing, sanitary, electrical, hardware, etc., having natural wear and tear
- Allowable structural and other deformations including expansion quotient
- The terms of work like painting etc., which are subject to wear and tear.
The Haryana Real Estate (Regulation and Development) Rules, 2017 (draft rules) defines “Defect Liability/Structural Defect” as,
actual physical damage/ defects to the designated load-bearing elements of the building, apartment or unit like faults, breakage or cracks, appearing over time in elements such as load bearing columns, walls, slabs, beams etc. which can affect the strength and stability of the apartment or the building and shall include any of the following, namely:-
1. defects due to design attributes of reinforced cement concrete (RCC) or structural mild steel (MS) elements of an engineered (structurally designed) building structure;
2. defects due to faulty or bad workmanship of RCC or MS work;
3. defects due to materials used in such RCC or MS work;
4. major cracks in masonry work that are induced as result of failures of RCC or MS work;
5. Any defect which is established to have occurred on account of negligence, use of inferior materials or non-adherence to the regulatory codes of practice by the promoter.
Explanation: – The promoter shall not be liable for any such 3 structural/ architectural defect induced by the allottee, by means of carrying out structural or architectural changes from the original specifications/ design.
Conclusion:
Thus, the clause “Defect Liability” will give rise to careful consideration on the quality of construction in a project by the promoters and in case of any structural defects, then gives the allottee/buyer a window to get the defects rectified by the promoter for a period of five years from the date of possession being handed over by the promoter and hence securing the interest and safeguarding the investment made by the allottee in a project building.
Best Practices –
1. Promoters to enter into contract with Contractors / Suppliers / Service providers back to back (min 5 years) to pass on the risk of defect liability.
2. If Contractors / Suppliers / Service providers are not covers for 5 years, then to rely on separate AMC’s to protect and mitigate financial risks.
3. Promoter to consider the increased cost due to defect liability as part of their project cost.
4. Training the inhouse team to aware of the Defect Liability and its importance especially to project team members
5. Be sensitive to customers / allottees questions on Defect Liability and how to reply to their concerns
well trained CRM can reply to such questions and concerns
have a system of / SOP on how to handle defect liability over 5 years
take professional services and support to know more about how Defect Liability impacts and what are the precautions to be taken / implement in a Real Estate Project
The home inspection will protect a home buyer from any pre defects in home before possession. Home inspection is a very necessary process regarding RERA 14.3 clause. Home inspection can be a formal document for to find out any pre-possession defects available in property. Most of the developers repaired the defects mention in the report. This defect can damage once again after regular use. Because of home inspection report, developer can never blame home buyer saying that the issues arise because of improper maintenance. Home inspection report gives RERA an evidence of the quality of workmanship and good quality or substandard material is used by the developer. To determine the validity of the claim under Section 14.3 of RERA, RERA can refer to this home inspection report.
If the date of possession is before the completion certificate issued by authority still defect liability period will be calculated from date of possession ? Secondly, if in group housing the date of possessions is spread over 2-3 years for different buyers of property, how will the defect liability period be calculated ?
If the defect liability clause is not mentioned in the builder buyer agreement. Is RERA still enforce builder for fix defect till 5 years?