Raj Kumar Gupta Vs Narang Constructions & Financiers Pvt. Ltd. (Delhi High Court)
Summary: The Delhi High Court, in Raj Kumar Gupta Vs Narang Constructions & Financiers Pvt. Ltd., held that non-attestation of a signed affidavit and Statement of Truth accompanying an application under Section 34 of the Arbitration and Conciliation Act, 1996, constituted a curable procedural defect and did not render the original filing non-est. Justice Neena Bansal Krishna further held that an increase in the number of pages during subsequent re-filing would not invalidate the original petition where the impugned arbitral award had already been furnished and the increase was attributable to the subsequent filing of arbitral proceedings. Accordingly, the Court condoned a delay of 52 days in rectification and re-filing of the petition.
The dispute arose from an arbitral award dated 15 March 2019, which the petitioner sought to challenge under Section 34 of the Arbitration and Conciliation Act, 1996. The ordinary limitation period, as recorded in the judgment, expired on 13 June 2019. However, owing to the summer vacation of the High Court, the petitioner filed the objections on 29 June 2019, immediately upon reopening of the Court. Subsequently, the petitioner filed an application under Section 151 of the Code of Civil Procedure, 1908 (CPC), seeking condonation of a delay of 52 days in re-filing the petition.
Want to Read the Complete Judgment?
You have read the free case summary. Unlock the full judgment, the detailed judicial reasoning and the downloadable PDF, along with every other premium judgment on TaxGuru.
Already subscribed? Log in
One subscription covers the entire premium judgment library, not just this case.