Case Name : M/s. Supertech Ltd. Vs Rajni Goyal (Supreme Court of India)
Related Assessment Year :
Courts :
Supreme Court of India
Become a Premium member to Download.
If you are already a Premium member, Login here to access.
M/s. Supertech Ltd. Vs Rajni Goyal (Supreme Court)
The Appellant – Builder inter alia submitted that – Possession of the flat was offered to the Respondent – Purchaser in December 2015 after obtaining the Completion Certificate for the building.
Even though the Agreement provided for delivery of possession by 31.10.2013, the delay occurred because of various legal impediments in timely completion of the project because of various Orders passed by the National Green Tribunal. The delay ought to be computed from 6 months after 31.10.2013, i.e. from 01.05.2014 by taking into consideration, ...