Advertisement
Advertisement
Skip to content
Follow Us on
Advertisement
TOP STORIES
Corporate Law

Home Buyer cannot reap benefits of her own delay in taking possession: SC

Case Law Details

Case Name
M/s. Supertech Ltd. Vs Rajni Goyal (Supreme Court of India)
Date of Judgement/Order
Only available for paid members
Advertisement
M/s. Supertech Ltd. Vs Rajni Goyal (Supreme Court) The Appellant – Builder inter alia submitted that – Possession of the flat was offered to the Respondent – Purchaser in December 2015 after obtaining the Completion Certificate for the building. Even though the Agreement provided for delivery of possession by 31.10.2013, the delay occurred because of various legal impediments in timely completion of the project because of various Orders passed by the National Green Tribunal. The delay ought to be computed from 6 months after 31.10.2013, i.e. from 01.05.2014 by taking into consideration, ...
This is premium content. Please become a Premium member. If you are already a member, login here to access the full content.
Advertisement

Join TaxGuru's Network for the latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

Leave a Reply

Your email address will not be published. Required fields are marked *