Sponsored
    Follow Us:
Sponsored

In Past 3 Years, the residential projects have been delayed too much in all cities and specially Gurugram. One Builder of Gurugram is ILD  which has recently been directed by the Department of Town & Country Planning (DTCP) to prepare and submit an action plan within a week for their completion.

If the ILD fails to fulfil the requirement within the specified time, then the department will recommend of registering an FIR against builder.

The Homebuyers of ILD Arete (Sector 33) and ILD Greens (Sector 37C) met the District Town Planner (DTP) for over three years delay in completion of work & various lack of amenities in the projects. The Homebuyers are planning to file a complaint against the Builder in Haryana RERA.

The project ILD Arete was launched in 2013 and now in 2020 it is only 60% Complete.

ILD’s another project, namely ILD Greens, was launched in 2008.  One of the homebuyers who bought flat in this project said the possession was supposed to be offered in October 2016 by Builder, eight years after booking. Almost Four Years have passed and only half of the towers are complete. Residents are not having permanent electricity, water & sewer connections.

District town planner (DTP) RS Batth directed the builder to finish the application works for necessities and complete the formalities to hand over basic amenities to the RWA. He has directed his team to inspect both the project sites thoroughly and check the construction status.

Sponsored

Tags:

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

Leave a Comment

Your email address will not be published. Required fields are marked *

Sponsored
Sponsored
Sponsored
Search Post by Date
August 2024
M T W T F S S
 1234
567891011
12131415161718
19202122232425
262728293031