GST Paid on Works Awarded Before July 2017 Reimbursable Subject to Verification: Kerala HC

Case Law Details

TaxGuru Citation
2026 taxguru.in 19839
Case Name
Mecone Construction Contractors Vs Chief Engineer (NW) & Ors. (Kerala High Court)
Appeal Number
Premium Access
Date of Judgement/Order
Premium Access
Subscribe to download.

Already Upgraded? Log in.

Advertisement

Mecone Construction Contractors Vs Chief Engineer (NW) & Ors. (Kerala High Court)

Summary: The Kerala High Court, comprising Justice Harisankar V. Menon, considered a writ petition filed by M/s Mecone Construction Contractors seeking reimbursement of the GST component attributable to works executed for the Military Engineer Services on or after 1 July 2017 pursuant to tenders invited before the introduction of GST. The petitioner had successfully participated in tender processes initiated through notices issued during 2015 and 2017, and the corresponding contracts had been awarded in April 2017, before GST came into force. Although various payments had been released towards execution of the contractual works, the petitioner alleged that the GST component relating to works executed after the introduction of GST had not been reimbursed.

The petitioner sought directions requiring the respondent authorities to reimburse the differential tax liability arising from the increase in applicable tax rates with reference to the rates prevailing on the last date for submission of the respective tenders. It also sought release of the outstanding final bill amounts and a declaration that the departmental communications dated 18 February 2022 and 5 April 2022 were inapplicable to the tenders in question. The petitioner relied upon Clause 27 of the Special Conditions governing reimbursement or refund on variation in taxes, which, according to the petitioner, required the contracting authority to reimburse any increase in taxes subsequent to submission of the tender. Accordingly, it contended that either the contract value should be enhanced to accommodate the additional tax burden or the GST actually remitted to the tax authorities should be reimbursed.

The High Court referred to its earlier decisions in Ganga Constructions Vs Assistant Executive Engineer, Irinjalakuda and Marycom Vs State of Kerala, wherein substantially similar controversies had been considered and reimbursement of the GST component attributable to the executed works had been recognised. The Court also referred to the judgment dated 17 March 2026 in Mary Matha Infrastructure Private Limited Vs State of Kerala, WP(C) No. 38282 of 2023, directing reimbursement of the GST paid by the contractor, and the subsequent Division Bench judgment dated 5 October 2026 in Writ Appeal No. 1845 of 2026. The Court considered the issue of reimbursement to be covered by these earlier judicial pronouncements.

Applying the principles laid down in the aforesaid judgments, the High Court held that, since the petitioner had admittedly been awarded the works pursuant to tenders floated before the introduction of GST, it was entitled to reimbursement of the GST component actually paid in respect of works executed on or after 1 July 2017. However, the Central Government Counsel submitted, on the basis of instructions received, that the petitioner had not furnished details of the tax amounts for which reimbursement was sought. Consequently, the Court recognised the petitioner’s entitlement in principle but did not independently quantify the reimbursable amount or direct unconditional payment of an unspecified sum.

Accordingly, the High Court disposed of the writ petition by directing the petitioner to furnish details of the tax sought to be reimbursed to the first respondent, the Chief Engineer (NW), within three weeks from the date of judgment. Upon receipt of the relevant particulars, the first respondent was directed to process the reimbursement claim with reference to the principles laid down in the four judgments cited by the Court. An appropriate decision was required to be taken within two months from the date of judgment and, if the decision was in favour of the petitioner, the amount was directed to be reimbursed within a further period of two weeks. The judgment thus recognises the entitlement to reimbursement of GST on qualifying pre-GST contracts while leaving the determination of the actual reimbursable amount to the competent contractual authority.

Cases Discussed

  • Ganga Constructions Vs Assistant Executive Engineer, Irinjalakuda (Kerala High Court); 2026 KHC OnLine 184; 2026:KER:13044; 12/02/2026. Relied upon by the High Court for the principle that the GST component attributable to contractual works must be paid or reimbursed to the contractor where the applicable tender conditions exclude GST from the quoted rates.
  • Marycom Vs State of Kerala (Kerala High Court); 2026 (6) KHC 75; (2026) 113 GSTL 190 (Ker.). Relied upon in support of the contractor’s entitlement to reimbursement of the GST component attributable to the works executed under the applicable contractual conditions.
  • Mary Matha Infrastructure Private Limited Vs State of Kerala (Kerala High Court); WP(C) No. 38282 of 2023; 2026:KER:22744; 17/03/2026. Relied upon by the Court as an earlier decision directing the respondent authorities to take effective steps to reimburse GST paid by a contractor in respect of works awarded before the introduction of GST.
  • State of Kerala Vs Mary Matha Infrastructure Private Limited (Kerala High Court, Division Bench); Writ Appeal No. 1845 of 2026; 2026:KER:76606; 05/10/2026. Relied upon by the Court as the appellate decision concerning the contractor’s entitlement to GST reimbursement. The Division Bench clarified that the reimbursable amount must be recalculated after considering the applicable VAT component and the differential GST liability in accordance with the directions contained in its judgment.
  • Jain Builders Vs Chief Engineer (NW) (Kerala High Court); WP(C) Nos. 22728 and 28767 of 2019; 28/10/2019. The judgment was produced by the petitioner as Exhibit P-12. It concerned contractual provisions governing reimbursement or deduction arising from variations in taxes during the subsistence of Military Engineer Services contracts and determination of the corresponding tax burden or benefit by the Garrison Engineer. It is not one of the four judgments expressly relied upon in the operative reasoning of the present judgment.

FULL TEXT OF THE JUDGMENT/ORDER OF KERALA HIGH COURT

Heard Sri. Deepu Thankan, learned counsel for the petitioner and Sri. Dinesh R. Shenoy CGC, for the respondents herein.

2. The petitioner is stated to be a contractor engaged by the Military Engineer Services for the execution of works contracts. Pursuant to the notices inviting tenders, at Exts. P1 to P3, all of which pertained to periods prior to the introduction of the Goods and Services Tax (GST), the petitioner submitted tenders and was the successful bidder. Accordingly, the petitioner was awarded the works in question.

3. The petitioner contends that, though various amounts have been disbursed towards the execution of the aforesaid works, the GST component in respect of the works executed on or after 01.07.2017 has not been paid.

4. In such circumstances, the petitioner has filed the captioned writ petition, seeking the following reliefs:

“(i) issue a writ of mandamus or any other appropriate writ or order or direction, directing the respondents 1& 2 to reimburse the difference amount consequent to the increase in percentage rates of taxes directly related to contract value with reference to prevailing rates on the last due date for receipt of tenders covered by Exhibit P-1 to P-3 Notice Inviting Tenders & Exhibit P-4 to P-6 Letter of Awarding contracts, forthwith;

(ii) issue a writ of mandamus or any other appropriate writ or order or direction, declaring that petitioner is entitled to get reimbursement of difference amount consequent to the increase in percentage rates of taxes directly related to contract value with reference to prevailing rates on last due date for receipt of tenders covered by Exhibit P-1 to P-3 Notice Inviting Tenders;

(iii) issue a writ of mandamus or appropriate writ or order or direction directing the respondents to release and disburse the final bill amount claimed by the petitioner with respect to the contracts performed by the petitioner based upon Exhibit P-3 to P-6 ignoring Exhibit P-13 & P- 14.

(iv) issue a writ of mandamus or appropriate writ or order declaring that Exhibit P-13 & P14 are not applicable to the tenders covered by Exhibit P-1 to P-3Notice Inviting Tenders:”

5. This Court notices that, according to the petitioner, Clause 27 of the Special Conditions on ‘Reimbursement/Refund on Variation in Taxes’, referred to in paragraph 10 of the writ petition, stipulates that any increase in taxes subsequent to the submission of the tender requires to be reimbursed by the awarder.

6. In the above circumstances, the petitioner contends that either the contract value requires to be enhanced to account for the increase in tax or, the GST remitted by the petitioner to the GST authorities requires to be reimbursed.

7. This Court, in Ganga Constructins v. Assistant Executive Engineer, Irinjalakuda [2026 KHC OnLine 184] and Marycom v. State of Kerala [2026 (6) KHC 75], has considered substantially similar issues and held that the GST component attributable to the works executed requires to be reimbursed to the concerned contractor in question.

8. A similar view was taken by a learned Single Judge of this Court in W.P.(C) No.38282 of 2023, by judgment dated 17.03.2026, wherein the respondents were directed to take steps to reimburse the GST amount paid by the petitioner therein. The appeal preferred against the said judgment was also dismissed by the Division Bench of this Court by judgment dated 05.10.2026 in Writ Appeal No.1845 of 2026.

9. On the face of the aforesaid judgments, this Court is of the opinion that, since the petitioner had admittedly been awarded the works pursuant to tenders floated prior to the introduction of GST, the petitioner is entitled to reimbursement of the GST component actually paid in respect of the works executed on or after 01.07.2017.

10. The learned Central Government Counsel, however, on the basis of the instructions received, submits that the petitioner has not furnished the details of the tax amounts sought to be reimbursed.

11. In any event, since the issue has already been considered in detail by the afore judgements, the captioned writ petition would stand disposed of as under;

i) The petitioner is directed to provide the details of the tax which requires to be reimbursed to the petitioner by the 1st respondent herein, within a period of three weeks from today.

ii) Upon production of such details, the 1st respondent shall process the claim with reference to the principles laid down in the four judgments referred to above.

iii) A decision in this regard shall be taken within a period of two months from today and if the decision is taken in favour of the petitioner, reimburse the amount within two weeks thereafter.

Advertisement

Author Info

CA Sandeep Kanoi
Qualification: Graduate, CA in Job / Business, DD
Company: Taxguru Consultancy
Location: Mumbai, Maharashtra
Articles Published: 25,380

Join TaxGuru's Network for the latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.