Sheo Raj Singh Vs Union of India & Anr. (Supreme Court of India)
The Supreme Court dismissed an appeal by affected landowners challenging the Delhi High Court’s decision to condone a delay of approximately 479 days in an appeal filed by the Union of India against enhanced land acquisition compensation. The Court held that the High Court’s exercise of discretion under Section 5 of the Limitation Act, 1963 was not arbitrary or clearly wrong and therefore did not warrant appellate interference.
The dispute originated from an order dated 31 October 2008 of the Reference Court in LAC No. 198/08 enhancing compensation payable to the landowners. The Union of India filed LA. App. No. 655/2010 before the Delhi High Court on 2 June 2010. Its appeal was delayed by 479 days. The High Court, by order dated 21 December 2011, accepted the explanation and condoned the delay subject to costs of Rs. 10,000.
The administrative record disclosed that counsel applied for a certified copy only on 22 April 2009, received it on 30 July 2009, and the department approved filing an appeal in August 2009. The file then moved through various offices. A court fee of Rs. 51,36,592 required budgetary approval and processing. A certified copy was misplaced, requiring another application. Funds were eventually approved and the court fee deposited in May 2010 before the appeal was presented in June 2010.
Want to Read the Complete Judgment?
You have read the free case summary. Unlock the full judgment, the detailed judicial reasoning and the downloadable PDF, along with every other premium judgment on TaxGuru.
Already subscribed? Log in
One subscription covers the entire premium judgment library, not just this case.