Case Law Details
Case Name : In re Haryana Power Generation Corporation Ltd. (GST AAR Haryana)
Appeal Number : Advance Ruling No. HAR/HAAR/R/2019-20/20
Date of Judgement/Order : 28/08/2020
Related Assessment Year :
Courts :
AAR Haryana Advance Rulings
Become a Premium member to Download.
If you are already a Premium member, Login here to access.
Sponsored
In re Haryana Power Generation Corporation Ltd. (GST AAR Haryana)
1. Whether coal rejects to be disposed of by way of sale at very nominal price by the power plants of the applicant attracts levy of compensation cess @ Rs. 400/- per MT?
Coal rejects to be disposed of by way of sale at very nominal price by the power plants of the applicant attracts levy of compensation cess @ Rs. 400/- per MT;
2. Whether coal rejects to be supplied by the power plants of the applicant is covered under HSN 2701 for levy of compensation cess @ Rs. 400/- per MT?
Coal rejects to be supplied by the power plants of the applicant is covered under HSN 2701 for levy of compensation cess @ Rs. 400/- per MT;