Uttar Pradesh Power Corporation Limited Vs Union of India & Others (Telangana High Court)
Summary: The Telangana High Court, in Uttar Pradesh Power Corporation Limited Vs Union of India & Others, considered a writ petition under Article 226 of the Constitution of India concerning the proposed consolidation of the Corporate Insolvency Resolution Processes (CIRPs) of KSK Mahanadi Power Company Limited, KSK Water Infrastructures Private Limited and Raigarh Champa Rail Infrastructure Private Limited. The petitioner, Uttar Pradesh Power Corporation Limited, sought directions requiring the respective Committees of Creditors and Resolution Professionals to approach the National Company Law Tribunal (NCLT), Hyderabad Bench, for consolidation of the three insolvency proceedings. It also sought disclosure of information relevant to consolidation, examination of the conduct of the Committees of Creditors, development of a framework for group insolvencies and restraint against further action concerning resolution plans.
The petitioner stated that KSK Mahanadi Power Company Limited was undergoing CIRP pursuant to an NCLT order dated 3 October 2019. Earlier, Punjab National Bank had filed I.A. No. 32 of 2020 in CP(IB) No. 492/07/HDB/2019 seeking consolidation of the insolvency proceedings. The NCLT rejected that application on 12 February 2021, observing that compulsory consolidation could create complications in dealing with the assets and liabilities of separate corporate debtors. The NCLT nevertheless observed that the Committees of Creditors could explore a common resolution applicant to achieve maximisation of asset value. The creditor challenged the rejection before the NCLAT, Chennai Bench, in Company Appeal (AT) (CH) (Ins) No. 46 of 2021. Further interlocutory proceedings concerning deferment of the resolution process were also instituted before the NCLT.
The High Court examined the earlier proceedings and observed that the petitioner had not independently approached the NCLT or NCLAT to challenge the withdrawal of the creditor’s appeal. Instead of granting the substantive relief seeking consolidation, the Court permitted the petitioner to file an appropriate application before the NCLT in the existing insolvency proceedings and raise all grounds available under law. It directed the NCLT to consider such application and pass appropriate orders within two weeks of its receipt. The High Court further directed that the resolution process would remain deferred until the NCLT decided the application. The writ petition was disposed of without costs.
Subsequent Supreme Court Development: The Committee of Creditors of KSK Mahanadi Power Company Limited challenged the High Court’s deferment direction. In Committee of Creditors of KSK Mahanadi Power Company Limited Vs M/s Uttar Pradesh Power Corporation Limited & Others (Supreme Court); Civil Appeal No. 11086 of 2024; 14/10/2024, the Supreme Court held that the High Court had no justification for deferring the CIRP under Article 226 after declining the principal relief of consolidation. It held that such interference breached the discipline established by the Insolvency and Bankruptcy Code, 2016. The Supreme Court accordingly set aside the High Court’s order only to the extent that it directed deferment of the CIRP. This subsequent ruling is material when considering the continuing legal effect of the Telangana High Court’s directions.
FULL TEXT OF THE ORDER OF TELANGANA HIGH COURT
This Writ Petition is filed seeking the following relief:
“… to issue a writ order direction in the nature of Mandamus declaring the action of:
a. The Respondent Nos. 3, 5 and 7 through the Respondent Nos. 2, 4 and 6 or independently to file an application for consolidation of CIRP of KSK Mahanadi Private Limited, KSK Water Infrastructures Private Limited and Raigarh Champa Rail Infrastructure Private Limited before the Learned NCLT, Hyderabad Bench for effective adjudication of this issue;
b. The Respondent Nos. 2, 4 and 6 i.e. the resolution professionals of KSK Mahanadi Private Limited, KSK Water Infrastructures Private Limited and Raigarh Champa Rail Infrastructure Private Limited to provide all such information as may be necessary for the Learned NCLT, Hyderabad to adjudicate upon the issue of consolidation of CIRP of KSK Mahanadi Private Limited, KSK Water Infrastructures Private Limited and Raigarh Champa Rail Infrastructure Private Limited;
c. The Respondent Nos. 1 and Respondent No. 8 to analyse and investigate the conduct of the Respondent No. 3, Respondent No. 5 and Respondent No. 7 i.e. the committee of creditors of KSK Mahanadi Private Limited, KSK Water Infrastructures Private Limited and Raigarh Champa Rail Infrastructure Private Limited from the perspective of whether these respondents have failed miserably in discharging the fiduciary duty foisted upon them by the IBC.
d. The Respondent Nos. 1 and 8 to expeditiously come up with a framework for group insolvencies to prevent any situation like the present.
e. The Respondent Nos. 2, 4 and 6 and Respondent Nos. 3, 5 and 7 i.e. the respective Resolution Professional and Committee of Creditors of all Corporate Debtors to not take any action including seeking approval of resolution plans for these companies till the pendency of the present writ petition…”
2. Considered the submissions of Sri B. Chandrasen Reddy, learned Senior Counsel representing Sri Amir Bavani, learned counsel appearing for the petitioner; Ms. N.V.R. Rajya Lakshmi, learned counsel representing Sri Gadi Praveen Kumar, learned Deputy Solicitor General of India, appearing for respondent No.1 and Sri Krishna Grandhi, learned counsel appearing for respondent Nos.5 and 7 and with their consent this writ petition is disposed of at the admission stage.
3. It is stated that the petitioner is a Company incorporated under the provisions of the Companies Act, 1956 and it is primarily responsible for distribution of the electricity in the State of Uttar Pradesh. It is further stated that respondent No.2-KSK Mahanadi Power Company Limited (“KSKMPCL”) being represented by its Resolution Professional Mr. Sumit Binani, is a public company currently undergoing Corporate Insolvency Resolution Process (“CIRP”) in terms of the Code as per the order, dated 03.10.2019 passed by the National Company Law Tribunal, Hyderabad (“NCLT”). Respondent No.3 is the Committee of Creditors of KSKMPCL being represented by Aditya Birla ARC Limited having 33.369% of the voting rights in the committee of creditors in KSKMPCL. Respondent No.4-KSK Water Infrastructures Private Limited (“KSKWIPL”). It is further stated that after initiation of Corporate Insolvency Resolution Process against the Corporate Debtors, one of the creditors of KSKMPCL i.e., Punjab National Bank has filed I.A.No.32 of 2020 in CP(IB) No.492/07/HDB/2019 on the file of NCLT seeking consolidation of CIRP of Corporate Debtors with two other companies. The said application was rejected by the NCLT vide order, dated 12.02.2021, wherein it was observed as follows:
“We being Adjudicating Authority, if direct CoC and RP of different Companies to sit together to resolve insolvency of different Corporate Debtors together then there will be chaotic situation relating to consolidation of assets and liabilities of all the Companies. In fact, inherent jurisdiction stated in Rule 11 of the NCLT Rules cannot be used to create such situation.
Before passing order we put it on record that CoC in all the above Companies may sit together and find out common resolution Applicant so as to achieve the object of maximization of assets of all the Corporate Debtors. We in our limited jurisdiction cannot direct consolidation of CIRP of different Corporate Debtors.”
4. Aggrieved by the same, Punjab National Bank (now Prudent ARC Limited) has preferred Company Appeal (AT) (CH) (Ins) No.46 of 2021 on the file of National Company Law Appellate Tribunal, Chennai Bench (for short “NCLAT”). It is further stated that during pendency of the appeal, IA(IBC)/374/2022 and IA(IBC)/403/2022 were filed in CP(IB) No.492/7/HDB/2019 on the file of NCLT and in the said applications, vide common order, dated 07.06.2022, the NCLT ordered as follows: No.492/7/HDB/2019 by the NCLT but the same were taken away in view of withdrawal of Company Appeal.
7. As seen from the material placed on record, the Financial Creditor has filed I.A.No.32/2020 in CP(IB) No.492/07/HDB/2019 on the file of NCLT seeking consolidation of CIRP of Corporate Debtors with two other companies and the said application was rejected by the NCLT vide order, dated 12.02.2021. Challenging the same, Financial Creditor filed Company Appeal (AT) (CH) (Ins) No.46 of 2021 on the file of NCLAT. During pendency of the appeal on the file of NCLAT, Financial Creditor has filed IA(IBC)/374/2022 and IA(IBC)/403/2022 in CP(IB) No.492/7/HDB/2019 on the file of NCLT and in the said applications, vide common order, dated 07.06.2022, the NCLT deferred the Resolution Process until further orders subject to the outcome of the appeal pending before the NCLAT and in the meanwhile granted stay of CIRP proceedings and directed the Resolution Professional not to undertake any such process till the IA(IBC)/374/2022 is disposed of. Admittedly, the petitioner herein has not filed any appeal or sought for any direction either from the NCLT or NCLAT. Since the petitioner has not filed any application either before the NCLT or NCLAT, it is not having any right to question the withdrawal of the appeal by the Financial Creditor.
8. In view of the above, this Court deems it appropriate to dispose of this Writ Petition by relegating the petitioner to file an appropriate application in CP(IB) No.492/7/HDB/2019 on the file of the NCLT and raise all grounds available under law. Upon filing such application, the NCLT is directed to examine the same and pass appropriate orders, in accordance with law, within a period of two(02) weeks from the date of receipt of such application. Until such time, the Resolution Process shall be deferred.
9. With the above observations, this Writ Petition is disposed of. There shall be no order as to costs.
As a sequel thereto, miscellaneous petitions, if any, pending shall stand closed.