State of Uttar Pradesh & Ors. Vs Satish Chand Shivhare And Brothers (Supreme Court of India)
The Supreme Court upheld the dismissal of the State of Uttar Pradesh’s appeal under Section 37 of the Arbitration and Conciliation Act, 1996, filed with a delay of 337 days, although it expressly found that the Allahabad High Court had relied on an incorrect legal proposition. The High Court had treated delays exceeding 120 days as incapable of condonation under the decision in N.V. International v. State of Assam. The Supreme Court clarified that this decision had subsequently been overruled by the three-Judge Bench in Government of Maharashtra v. Borse Brothers Engineers and Contractors Private Limited. Nevertheless, the State’s failure to establish sufficient cause under Section 5 of the Limitation Act, 1963, independently justified refusal of relief.
Background: Construction Contract and Arbitration Award
The dispute originated from a contract dated 22 September 1998 for constructing a Gymnastic Hall at Eklavya Sports Stadium, Agra, for ₹48,55,800, with a completion period of twelve months. Following disputes concerning additional work, delayed payments and final bills, the contractor invoked arbitration.
The arbitral tribunal, presided over by a former Allahabad High Court Judge, examined the pleadings, evidence and approximately eighteen issues. It awarded the contractor ₹40,61,264, finding, among other things, that additional work had been undertaken, payments were delayed and the State’s final bill was unreliable.
Want to Read the Complete Judgment?
You have read the free case summary. Unlock the full judgment, the detailed judicial reasoning and the downloadable PDF, along with every other premium judgment on TaxGuru.
Already subscribed? Log in
One subscription covers the entire premium judgment library, not just this case.