NOTIFICATION NO 120/2006, dated 16-5-2006
S.O. 723(E).—In exercise of the powers conferred by clause (6C) of section 10 of the Income-tax Act, 1961 (43 of 1961), the Central Government hereby declares that any income arising to the foreign companies specified in column (2) of the table given below, by way of royalty or fees for technical services received in pursuance of the agreements specified in column (3) of the table, entered into by them with the Government of India for providing the services specified in column (4) of the table, in or outside India relating to the projects connected with security of India, shall not be included in computing the total income of the said company under the Income – tax Act, 1961, provided that the income by way of royalty would be exempt from taxation if such income has arisen on or after the 1st April, 2003.
TABLE
Sl. No
|
Name & Address of Foreign Company
|
Contract Number and Date
|
Nature of technical services
|
(1)
|
(2)
|
(3)
|
(4)
|
1
|
M/s. Snecma Moteurs, 2, boulevard du General Martial Valin 75724-Paris Cedex 15 -France
|
KAV/FFEC/1081/GTRE dated 28.09.2001
|
Technical Audit of Design Works relating to The Kaveri Engine Programme
|
2
|
Federal State Unitary Enterprise “Russian Technologies”, 1, 1-ja Tveskaja-Yamskaja str., Moscow, 125818,
|
KAV/FFEC/1020/GTRE dated 01.03.2000
|
Exploratory Altitude Testing of Kaveri Engine
|
3
|
Federal State Unitary Enterprise, ‘Rosoboronexport”, 27/3, Stromynka Street, Moscow, Russia, 107076
|
Amendment No. 335634211707 to KAV/FFEC/1020/GTRE dated 01-03-2000
|
Exploratory Altitude Testing of Kaveri Engine
|
4
|
Federal State Unitary Enterprise, “Rosoboronexport”, 27/3, Stromynka Street, Moscow, Russia, 107076
|
P/135634011927-KAV/FFEC/1045/GTRE dated 22.03.2002
|
Fan Casing Containment Test for Kaveri Engine
|
5
|
Federal State Unitary Enterprise, ‘Rosoboronexport”, 27/3, Stromynka Street, Moscow, Russia 107076
|
P/135634011930-KAV/FFEC/1042/GTRE dated 22.03.2002
|
Testing for Main Combustor at Sea level and Altitude conditions
|
6
|
Scientific Centre, Russian Federation, M/s Gromov Flight Research Institute Zhukovski, Moscow Region.
|
KAV/FFEC/799/GTRE dated 22.03.2002
|
Various Technical services for Kaveri Engine
|
7.
|
M/s. Kolb+Baumann Prazisions-Messeuge Daimlerstra Be 24 D63741, Aschaffenburg, Germany
|
GTRE/MMG/FEKV/3026/ 02/FPO/03 dated 14.07.2003
|
Consultancy services for CMM using ‘KOBA STEP GAUGE” with GUK-S Software.
|
8.
|
M/s. ACRI, 260, Route Du Pin Montard BP 234-06904 Sophia Antipolis, France
|
KAV/FFEC/1065/GTRE dated 31.10.2001
|
Development of Software using 3D flow field analysis for the fabrication of Combustor for Kaveri Engine.
|
9.
|
Test Devices INC., 6, Loring Street, Hudson MA 01749, USA
|
GTRE/MMG/FEKV/3017/ 02/FPC/A/03 dated 30.09.2003
|
Over speed & Burst margin test on K6HPC Rotor assembly
|
10.
|
Test Devices INC., 6, Loring Street, Hudson MA 01749, USA
|
GTRE/MMG/FEKV/3018/ 02/FPC/A/03 dated 17.10.2003
|
Over speed & burst margin test on K6 Fan Rotor assembly
|
11.
|
Test Devices INC., 6, Loring Street, Hudson MA 01749, USA
|
GTRE/MMG/FEKV/3007/ 03/FPC/A/03 dated 20.03.2004
|
Design, Analysis, Testing & Optimization of Damper for the LP Turbine Rotor Blade
|
12.
|
MTU Aero Engines, GmbH & Co. KG Represented by MTU Aero engines Verwaltungs GmbH Postfach 50 06 40, 80976 Muenchen Germany
|
GTRE/MMG/FEKV/3009/ 03/FPC/A/04 dated 23.08.2004
|
Over speed & Burst Margin Test on K6HP Turbine Rotor Assembly
|
13.
|
MTU Aero Engines, GmbH & Co. KG Represented by MTU Aero engines Verwaltungs GmbH Postfach 50 06 40, 80976 Muenchen Germany
|
GTRE/MMG/FEKV/300 8/03/FPC/A/04 dated 23.08.2004
|
Over speed & Burst Margin Test on K6 LP Turbine Rotor Assembly
|
14.
|
M/s. Samtech S.A. Parc Scoemtofoque Du Sart Tilman Rue Des Chasseurs Ardemmais 8, B-4031, Angleur (Belgium)
|
GTRE/MMG/FEKV/301 9/02/FPC/03 dated 29.08.2003
|
Dynamic Analysis under Blade off condition of Kaveri engine
|
15.
|
Applied Technology Consultants Ltd., Holland House, 30, Old street, Clevedon BS 21 6BY, UK
|
KAV/FFEC/997/GTRE dated 31.08.1999
|
Consultancy for Reheat System Design Review/Audit
|
16.
|
Applied Technology Consultants Ltd., Holland House, 30, Old street, Clevedon BS 21 6BY, UK
|
KAV/FFEC/996/GTRE dated 31.08.1999
|
Consultancy for HP Turbine Risk Analysis/Review
|
17.
|
Applied Technology Consultants Ltd., Holland House, 30, Old street, Clevedon BS 21 6BY, UK
|
KAV/FFEC/998/GTRE dated 31.08.1999
|
Consultancy for Weight Reduction Study
|
18.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS 21 7RA, UK
|
KAV/FFEC/1011 /GTRE dated 28.10.1999
|
Consultancy for Thermal and Hydraulic Modelling of Kaveri Lubrication System
|
19.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS 21 7RA, UK
|
KAV/FFEC/1027A/GTRE dated 14.09.2000
|
Consultancy for Kaveri Fan Aerodynamic and Mechanical Design Review/Audit and enhancement.
|
20.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS 21 7RA, UK
|
KAV/FFEC/1028/GTRE dated 14.09.2000
|
Consultancy for Critical Design Review of the Kaveri Engine Project
|
21.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1027/GTRE dated 14.09.2000
|
Consultancy for Accelerated Simulated Mission Endurance Test (ASMET) Cycle and test schedule definition and development programme integration.
|
22.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1088/GTRE dated 12.06.2001
|
Consultancy for Kaveri Integrated Test, Development and Procurement programmes
|
23.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1075/GTRE dated 05.07.2001
|
Consultancy for Kaveri PFRT Fan Aerodynamic Design 3D Blade-to-Blade and Viscous Analysis (ATC 506 issue 01)
|
24.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1074/GTRE Dated 25.08.2001
|
Consultancy for Kaveri K4 Build 06 HP Compressor Blade Stage 1 Failure Investigation and Follow-up (ATC 507 issue 01)
|
25.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1080/GTRE Dated 25.08.2001
|
Consultancy for Review and Proposal for the Resolution of Vibration Problems in the Kaveri Engine
|
26.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA UK
|
KAV/FFEC/1089/GTRE Dated 12.06.2001
|
Consultancy for Design Review and Audit of High Temperature High Pressure Heat Transfer Rig
|
27.
|
Applied Technology Consultants Ltd., Brunel House, 5, Elton Road, Clevedon BS21 7RA, UK
|
KAV/FFEC/1080/GTRE Dated 22.01.2004
|
Consultancy for Kaveri K5 & K8 Compressor Blade Stage I vibration & Rub Investigation Problems in the Kaveri Engine
|
[F.No.200/95/2004-ITA-I]