In re MTS-EILE (JV) (GST AAR Rajasthan)
Summary: The Rajasthan Authority for Advance Ruling considered an application filed by M/s MTS-EILE (1V), Jaipur, concerning the applicable GST rate for an ongoing composite works contract relating to FSTP infrastructure projects under Contract Package No. RSTDSP/FSTP-9 Towns/03. The tender was invited on 24.04.2022, the bid was submitted on 28.06.2022, the Letter of Acceptance was issued on 30.09.2022 and the Notice to Proceed was issued on 28.11.2022. The applicant had considered GST @12% (6% CGST + 6% SGST) at the tender and bid stages, while GST @18% (9% CGST + 9% SGST) was subsequently paid on works executed and billed on or after 19.07.2022 pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13.07.2022. The applicant sought a ruling on whether 12% GST was applicable on the tender/bid dates and whether the subsequent increase to 18% constituted an additional statutory tax liability/change in tax for the ongoing contract. At the personal hearing on 13.07.2026, the applicant requested withdrawal of the application with liberty to file a fresh application. The Authority considered the withdrawal request and recorded that no ruling was given.
Main Article / Analysis
Issue Before the Authority
The issue raised by M/s MTS-EILE (1V),5/2, Shahid Amit Bhardwaj Marg, JAIPUR, Rajasthan-302017(hereinafter ‘the applicant, is fit to pronounce advance ruling as they have deposited prescribed Fee under CGST Act and it falls under the ambit of the Section 97(2)given as under:
(a) Classification of goods and/or services or both
(b) Applicability of a notification issued under the provisions of the Act
The order records the statutory framework governing advance rulings, including Section 102 concerning rectification, Section 103 concerning the binding nature of an advance ruling, Section 104 concerning an advance ruling obtained by fraud or suppression of material facts or misrepresentation of facts, and Section 100 concerning an appeal against an advance ruling.
Applicant’s Works Contract and Relevant Dates
The Applicant has been awarded works relating to construction, testing, commissioning, operation and maintenance of FSTP (Faecal Sludge Treatment plant infrastructure projects by Rajasthan Urban Infrastructure Development Project (RUIDP) and respective Nagar Parishads/Nagar Palikas for various towns under Contract Package No. RSTDSP/FSTP-9 Towns/03.
The tender for the subject work was invited on 24.04.2022, the bid was submitted on 28.06.2022, Letter of Acceptance (LOA) was issued on 30.09.2022 and Notice to Proceed was issued on 28.11.2022. The contract is an ongoing composite works contract service.
The applicant stated that, at the time of tendering and submission of bid, GST @12% (6% CGST + 6% SGST) had been considered and quoted in the bid price based on the understanding of the applicable GST notifications prevailing at that time.
Change in GST Rate
The applicant stated that, subsequently, after 18.07,2022, GST @18% (9% CGST + 9% SGST) had been levied and paid on all works executed and billed under the contract, resulting in an additional GST burden of 6% over and above the GST considered in the bid.
The applicant submitted that GST @12% (6% CGST + 6% SGST) was prevailing and applicable for the subject STP/FSTP/Waste Water infrastructure works contract on the date of tender invitation i.e. 24.04.2022 and on the date of bid submission i.e. 28.06.2022 under the relevant provisions of Notification No. 11/2017-Central Tax (Rate) as amended up to that date.
The applicant further submitted that, pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13,07.2022, the concessional GST entry applicable to the said works contract stood omitted/modified and GST @18% (9% CGST + 9% SGST) became applicable on works executed and billed on or after 19.07.2022.
The applicant stated that, due to the change in GST rate from 12% considered at the time of bidding to 18% paid during execution of the contract, it had incurred an additional GST burden of 6% over and above the tax component considered in the original bid price.
Questions Raised by the Applicant
Q1. Whether GST @12% (6% CGST + 6% SGST) was correctly applicable for our FSTP (Faecal Sludge Treatment plant: Similar to STP/WWW) infrastructure works contract on the date of tender Invitation i.e. 24.04.2022 and on the date of bid submission i.e. 28.06.2022 under Notification No. 11/2017-Central Tax (Rate), considering that the bid was prepared and submitted based on the GST provisions prevailing on those dates?
Q2) Whether the increase in GST from 12% (considered in the bid on 24.04.2022 / 28.06.2022) to 18% paid on works executed and billed on or after 19.07.2022 pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13.07.2022 shall be treated as additional statutory tax liability/change in tax for the said ongoing contract?
The subject matter concerned the GST rate applicable to works contract services. TaxGuru’s material on Works Contract in GST also addresses the rate prescribed under Serial No. 3 of Notification No. 11/2017-Central Tax (Rate).
Personal Hearing and Withdrawal
In the matter, personal hearing was granted to the applicant on 13.07.2026 Mr. Jaideep Dullar, Mr. Rajat lain, Mr. Pankajj Goenka Authorized Representative appeared for personal hearing. They reiterated the submission already made by them. During P.H. they stated to withdraw this application with the liberty to file fresh application.
The applicant during P.H. on 13.07.2026 stated to withdraw this application with the liberty to file fresh application.
Outcome
Since the applicant has requested for withdrawal of the application therefore, their request to withdraw the application is considered. Hence, no ruling is given.
Accordingly, the Authority did not decide the substantive questions concerning the applicability of GST @12% on the tender/bid dates, the subsequent GST rate of 18%, or whether the additional 6% constituted an additional statutory tax liability/change in tax for the ongoing contract. The applicant’s stated liberty to file a fresh application is recorded as part of the withdrawal request, and no ruling was given on the questions raised.
Alternative SEO Titles
GST Rate Dispute: MTS-EILE (JV) Withdraws AAR Application
AAR Rajasthan: MTS-EILE (JV) Application Withdrawn, No Ruling
MTS-EILE (JV) Withdraws GST Rate Application Before AAR Rajasthan
AAR Rajasthan Records Withdrawal of MTS-EILE GST Application
GST Rate on FSTP Works Contract: AAR Application Withdrawn
FULL TEXT OF THE ORDER OF AUTHORITY FOR ADVANCE RULING, RAJASTHAN
In terms of Section 102 of the Central Goods and Services Tax Act, 2017 and the Rajasthan Goods and Services Tax Act, 2017 (hereinafter referred to as the CGST Act and the RGST Act respectively), this Advance Ruling may be amended by the Authority for Advance Ruling so as to rectify any error apparent on the face of the record, if such error is noticed by the Authority on its own motion or is brought to its notice by the applicant or the concerned officer or the jurisdictional officer within a period of six months from the date of the order. Provided that no rectification which has the effect of enhancing the tax liability or reducing the amount of admissible input tax credit shall be made unless the applicant or the appellant has been given an opportunity of being heard.
2. Under Section 103(1) of the CGST Act, 2017 and the RGST Act, 2017, this Advance Ruling pronounced under Chapter XVII of the Acts shall be binding only: (a) on the applicant who had sought it in respect of any matter referred to in Section 97(2) of the Acts; and (b) on the concerned officer or the jurisdictional officer In respect of the applicant.
3. In terms of Section 103(2) of the CGST Act, 2017 and the RGST Act, 2017, this Advance Ruling shall be binding unless the law, facts or circumstances supporting the original ruling have changed.
4. Under Section 104(1) of the CGST Act, 2017 and the RGST Act. 2017, where the Authority finds that the Advance Ruling has been obtained by the applicant by fraud or suppression of material facts or misrepresentation of facts, it may, by order, declare such ruling to be void ab initio and thereupon all the provisions of the Acts or the Rules made thereunder shalt apply to the applicant as if such Advance Ruling had never been made
5. Any appeal against this Advance Ruling shall lie before the Appellate Authority for Advance Ruling, Rajasthan, in terms of Section 100 of the CGST Act, 2017 and the RGST Act, 2017. Such appeal shall be filed within thirty days from the date on which the ruling is communicated to the applicant, the concerned officer or the jurisdictional officer, as the case may be. The Appellate Authority may, if satisfied that the appellant was prevented by sufficient cause from presenting the appeal within the said period of thirty days, allow it to be presented within a further period not exceeding thirty days.
The issue raised by M/s MTS-EILE (1V),5/2, Shahid Amit Bhardwaj Marg, JAIPUR, Rajasthan-302017(hereinafter ‘the applicant, is fit to pronounce advance ruling as they have deposited prescribed Fee under CGST Act and it falls under the ambit of the Section 97(2)given as under:
(a) Classification of goods and/or services or both
(b) Applicability of a notification issued under the provisions of the Act
A. SUBMISSION OF THE APPUCANTfin brief):-
Brief facts of the case:
a) The Applicant has been awarded works relating to construction, testing, commissioning, operation and maintenance of FSTP (Faecal Sludge Treatment plant infrastructure projects by Rajasthan Urban Infrastructure Development Project (RUIDP) and respective Nagar Parishads/Nagar Palikas for various towns under Contract Package No. RSTDSP/FSTP-9 Towns/03. The tender for the subject work was invited on 24.04.2022, the bid was submitted on 28.06.2022, Letter of Acceptance (LOA) was issued on 30.09.2022 and Notice to Proceed was issued on 28.11.2022. The contract is an ongoing composite works contract service.
b) The Applicant seeks clarification regarding the applicable GST rate prevailing on the date of tender/bid submission for the subject works contract. At the time of tendering and submission of bid, the Applicant had considered and quoted GST @12% (6% CGST + 6% SGST) In the bid price based on the understanding of the applicable GST notifications prevailing at that time.
c) Subsequently, after 18.07,2022, GST @18% (9% CGST + 9% SGST) has been levied and paid by the Applicant on all works executed and billed under the contract. As a result, the Applicant has incurred an additional GST burden of 6% over and above the GST considered In the bid.
d) In the above background, clarification is sought as to whether GST @12% was correctly applicable on the date of tender/bid submission i.e. 24.04.2022/28.06.2022 for the subject contract and, consequently, whether the additional 6% GST paid after 18.07.2022 on execution of works under the ongoing contract constitutes an additional statutory tax liability admissible under the contract conditions.
B. INTERPRETATION AND UNDERSTANDING OF APPLICANT ON QUESTION RAISED (IN BRIEF}
a) We have been awarded works relating to Design, Supply, Construction, Testing, Trial Run, Commissioning and 5 years’ Operation & Maintenance FSTP (Faecal Sludge Treatment plant Infrastructure projects by Rajasthan Urban Infrastructure Development Project (RUIDP) and respective Nagar Parishads/Nagar Palikas for various towns under Contract Package No. RSTDSP/FSTP-9 Towns/03,
b) The tender for the subject work was invited on 24.04.2022 and the bid was submitted on 28.06.2022. The Letter of Acceptance (LOA) was issued on 30.09.2022 and Notice to Proceed was issued on 28.11.2022. The contract is presently under execution.
c) At the time of tendering and submission of bid, we had considered GST @12% (6% CGST+ 6% SGST) in the bid price based on the GST provisions and notifications prevailing on the dates of tender invitation and bid submission.
d) Subsequently, pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13.07.2022, GST @18% (9% CGST + 9% SGST) became applicable on works executed and billed on or after 19.07.2022, and accordingly we have paid GST @18% on ail such works executed under the contract.
We respectfully submit that GST @12% (6% CGST + 6% SGST) was prevailing and applicable for the subject STP/FSTP/Waste Water infrastructure works contract on the date of tender invitation I.e. 24.04.2022 and on the date of bid submission i.e. 28.06.2022 under the relevant provisions of Notification No. 11/2017-Central Tax (Rate) as amended up to that date. Accordingly, while preparing and submitting the financial bid, we had considered GST @12% in the quoted contract price.
Subsequently, pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13,07.2022, the concessional GST entry applicable to the said works contract stood omitted/modified and GST @18% (9% CGST + 9% SGST) became applicable on works executed and billed on or after 19.07.2022. Accordingly, we have discharged GST liability @18% on all such works executed under the ongoing contract.
Due to the change in GST rate from 12% considered at the time of bidding to 18% paid during execution of the contract, we have incurred an additional GST burden of 6% over and above the tax component considered in the original bid price. Therefore, clarification/ruling is sought regarding correctness of applicability of GST @12% on the tender/bid dates and whether the subsequent increase to 18% constitutes an additional statutory tax liability/change In tax in respect of the ongoing contract.
C. QUESTIONS ON WHICH THE ADVANCE RUUNG IS SOUGHT:
Q1. Whether GST @12% (6% CGST + 6% SGST) was correctly applicable for our FSTP (Faecal Sludge Treatment plant: Similar to STP/WWW) infrastructure works contract on the date of tender Invitation i.e. 24.04.2022 and on the date of bid submission i.e. 28.06.2022 under Notification No. 11/2017-Central Tax (Rate), considering that the bid was prepared and submitted based on the GST provisions prevailing on those dates?
Q2) Whether the increase in GST from 12% (considered in the bid on 24.04.2022 / 28.06.2022) to 18% paid on works executed and billed on or after 19.07.2022 pursuant to Notification No. 03/2022-Central Tax (Rate) dated 13.07.2022 shall be treated as additional statutory tax liability/change in tax for the said ongoing contract?
D. PERSONAL HEARING:
In the matter, personal hearing was granted to the applicant on 13.07.2026 Mr. Jaideep Dullar, Mr. Rajat lain, Mr. Pankajj Goenka Authorized Representative appeared for personal hearing. They reiterated the submission already made by them. During P.H. they stated to withdraw this application with the liberty to file fresh application.
E. WITHDRAWAL OF APPLICATION:
The applicant during P.H. on 13.07.2026 stated to withdraw this application with the liberty to file fresh application.
Since the applicant has requested for withdrawal of the application therefore, their request to withdraw the application is considered. Hence, no ruling is given.






