The Real Estate (Regulation & Development) Act 2016 was enacted fully w.e.f., 1st May 2017 and presently it is effective and has been implemented in most of the States and Union Territories.

Jammu & Kashmir is the latest state / UT to notify Rules in August 2020 and announced that it will appoint the RERA Authority for effective implementation of the Act in Jammu & Kashmir.

The implementation of The Real Estate (Regulation & Development) Act 2016 by the states and setting up of the Adjudication mechanism including the Appellate Tribunals to hear the matters relating to violation of the provisions of the Act by the Promoters and Allottees, has resulted in speedy disposal of the matters thereby resulting in giving relief to both Allottees and Promoters. Approximately, about 75,000 projects have been registered and as many as 70,000 complaints have been disposed of by the Real Estate Regulatory Authorities.

On 1st may 2021, 4 years completed and stepping into 5th year of implementation of the RERA. RERA Authorities have implemented the processes of Registration of the Project, Agent Registration, Extension, modification, Complaint filing, redressal mechanism etc in an effective and efficient manner. Various efforts were made by the Authorities to educate various stakeholders in the Industry, their roles and responsibilities in order to achieve the objectives of the Act.

Every stakeholder plays a vital and important role under the Act. Viz., RERA Authorities, Promoters, Landowners, Allottees, Real Estate Agents, Bankers, Financial institutions, vendors, investors, lenders, government agencies, department, professionals like Engineer, Architect and a Chartered Accountant. I presume that each stakeholder understood the importance of RERA, it’s objective. Efforts were made in complying with the various provisions under the Act, Rules and Regulations.

The Real Estate (Regulation & Development) Act 2016 is a transformation statute for a Real Estate Business. The truest implementation of the statute will bring unbelievable results in the Industry and to the Country.

Over the last 4 years of implementation, RERA Authorities have focused and spend their energy in exercising the regulatory provisions of the Act / Statute. Act has an inbuilt provision wherein the States and RERA Authorities have obligation to implement the development aspects. These development aspects include strengthening various practices, ease the procedures, recommendations for improvement in policy matters.

During these 4 years, the RERA Authorities have operationlised the Website, wherein the promoters have published all the relevant details of the project. With a click of a button, the stakeholders can access these data and ensure themselves about the correctness of the project and its details.

With the implementation of the website, much more benefits to the buyers of the real estate project. Buyers can verify the details before they make the decision of buying the units in the project.

Over the last four years, the Authorities have exercised powers vested under the Act, Rules and levied the penalty on the project for non-compliance of various provisions under the Act.

Even though four years is complete, still a long way to go.

Challenges before the RERA Authorities 

1. Bringing all unregistered projects under its purview

2. Enforcing compliance for the orders passed by the Authority, Adjudicating officer. Especially in relation to Allottees complaint and orders thereon

3. Enforcing compliance of all applicable provisions under the Act

4. Continuous monitoring of the progress of development of the project and timely delivery of units to the buyers.

5. Bringing all allied laws in line with RERA Act and Rules

6. Making RERA the ultimate statute to govern the Real Estate projects

7. Bringing development aspects and implementation of the same, helping industry in Ease of Doing business

Section 32 of the Act gives the power to the Authority to facilitate the growth and promotion of a healthy, transparent, efficient and competitive real estate sector make recommendations to the appropriate Government of the competent authority, as the case may be, on –

(a) protection of interest of the allottees, promoter and real estate agent

(b) creation of a single-window system for ensuring time-bound project approvals and clearances for timely completion of the project

(c) creation of a transparent and robust grievance redressal mechanism against acts of omission and commission of competent authorities and their officials

(d) measures to encourage investment in the real estate sector including measures to increase financial assistance to the affordable housing segment

(e) measures to encourage construction of environmentally sustainable and affordable housing, promoting standardization and use of appropriate construction materials, fixtures, fittings and construction techniques

(f) measures to encourage grading of projects on various parameters of development including grading of promoters

(g) measures to facilitate amicable conciliation of disputes between the promoters and the allottees through dispute settlement forums set up by the consumer or promoter associations

(h) measures to facilitate digitization of land records and system towards conclusive property titles with title guarantee

(i) to render advice to the appropriate Government in matters relating to the development of the real estate sector

(j) any other issue that the Authority may think necessary for the promotion of the real estate sector

Changes/transformation in real estate business and practices – Post RERA –

1. Prior Registration of Real estate projects is mandatory – every project required to obtain the registration from RERA Authority before marketing, advertise, collect advance, invite people etc

2. Authority either grants or rejects the application for registration within 30 days – further the Act mentions the deemed registration if the Authority fails to issue the registration within 30 days of the application

3. Details of registration granted by RERA for the project available on the RERA portal

4. Details of the Project including Number/ types of apartments or plots booked, approvals granted, NOC’s, the status of the project etc are published by the Authority on RERA Portal

5. Sanctioned plan, layout plan, stage-wise schedule of completion of the project including the provisions for civic infrastructures like water, sanitation and electricity available on RERA portal

6. RERA Registration Number shall be displayed on Project Site

7. All advertising or marketing collaterals shall carry Rera Registration Number, RERA Website address – Print, hoarding, social media, SMS, Television etc

8. RERA Registration number shall be displayed prominently on advertising or marketing collateral.

9. Promoter is responsible for obtaining leasehold certificate, commencement and completion/ occupancy certificate/completion certificates for all projects

10. Shall provide Estimated Cost of the Project while an application for registration. This means the promoters of the project shall prepare a comprehensive plan considering the various aspects/situation/risks in the life cycle of the development of the project.

11. Landowner and Developer both are responsible under the Act as Promoter and liable to deliver to the allottees in terms of the agreement entered.

12. Financial management under the Act is mandatory from inception to completion – collection, deposit and withdrawal of money

13. 70 % amount realised from the allottees shall be deposited into RERA Designated Project Bank Account

14. Amount shall be withdrawn based on % of completion of development work

15. Withdrawal of money from RERA Designated Project Bank Account shall be supported by Architect, Engineer and CA certificates certifying the % of completion of development work

16. RERA Annual Audit Due date is 30th Sep of every year (6 months from the end of financial year) – Applicable to all projects from inception to completion.

17. RERA Audit report shall be uploaded along with quarterly updates (Sep quarter)

18. Quarterly Updates due date – 15 days from the end of the quarter (K RERA)

19. Any modification in the sanctioned plan shall require Section 14 Compliance – there cannot be the unilateral decision of the promoter. Promoter shall obtain consent from the allottees for any modification in plan.

20. Change of promoter/transfer of rights requires Section 15 compliance

21. 2/3rd Consent of Allottees required for modification of plan or change of promoter

22. Extension application for End Date (renewal) for the project is mandatory. This means every promoter shall plan and develop the project and deliver within the timelines provided.

23. File application for extension 3 months before End Date

24. All Compliances shall be in place (Quarterly updates, Annual Audit etc to seek for extension of end-date)

25. Extension of Registration in accordance with Section 6 of the Act

26. Revocation of Registration of Project by authority as per Section 7 – Suomoto or based on a complaint received

27. Display of defaulter list on the website of the Authority and inform all other states about such defaulter

28. Formation of Allottees Association once major bookings are to be done as per Section 11 – it is mandatory for the promoter to enable the formation of Association of Allottees once major booking in the project is done. Such Association shall be in accordance with the local applicable laws.

29. Responsible for compensation for loss or damage caused due to incorrect/ false statement made in prospectus or notice of advertisement or in relation to the model apartment, plot or building – Section 12

30. Communication to Allottees from time to time about the progress of development works in the project through any medium

31. Mention of schedule of development of the projects part of Agreement for Sale

32. Mention the Carpet Area in all documents (marketing, offer documents, agreement, sale deed etc) – Carpet Area is the unit of measurement under RERA.

33. Car Park allotment only for the exclusive use of private residence of the project. Such car parks shall be allotted in terms of sanctioned plan

34. No Escalation in price once the agreement is entered with the allottees except in case of an increase in statutory levies. Means promoter shall consider all possible escalation costs during the tenure of development of the project as part of the estimated cost of the project.

35. Defect Liability is for 5 years – consider the cost of attending/rectifying such defects as part of the cost of the project. Such defects shall be attended within 30 days of notice by the allottees in the project.

36. Title Defect – Lifetime warranty

37. Appointment of RERA Registered Agent only to promote/market the RERA Registered project

38. Periodical training of Agents / Channel partners and train them on the importance of communication with customers

39. Filing of completion application on receipt of Completion certificate and completion of developments works and all obligations as per Agreement for sale

40. Change of RERA Project designated Bank Account with prior approval of the Authority.

41. Promoter Shall not collect more than 10 % of the cost of the unit without entering into Agreement of Sale with the allottees

42. Agreement for Sale shall be registered

43. Follow Agreement of sale (mandatory) format as notified by RERA – Rule 8A

44. Cash collection is not permitted as per Agreement for Sale

45. After executing an agreement for sale, not to mortgage or create a charge on the apartment, plot or building

46. Cancellation of allotment only in terms of the agreement for sale

47. Execute a registered conveyance deed of the apartment, plot or building within 3 months from the date of issue of Occupancy Certificate

48. Providing and maintaining essential services until handover the maintenance to the Association of allottees

49. Handing over of the common areas, project land to the Association of Allottees as per Section 17 of the Act

50. Penalties for noncompliance are based on % of Estimate Cost of the Project Sec 59 to Sec 68 of the Act

51. Proper clauses in Joint Development Agreement in relation to roles, responsibilities, a mandatory deposit of landowner share of realization of money from the allottees into the project designated bank account, restrictions on withdrawal and utilization for the development of the project and all other compliances under RERA shall be deliberated and mentioned.

52. Construction insurance and Title Insurance is mandatory for the Project.

53. Same Rate of interest as compensation (maximum of SBI MCLR + 2%) in case of delay by the promoter for completion or delay of payment of installment by allottees.

54. Speedy dispute redressal mechanism and timely disposal of complaints under the Act.

55. Promoter can forfeit only booking amount in case of cancellation by the Allottee.

*****

CA.Vinay Thyagaraj is a Practicing Chartered Accountant from Bangalore. You can write a mail to vinay@vnv.ca for any queries.

Sponsored

Tags:

Author Bio

CA Vinay Thyagaraj, practicing Professional in the area of Real Estate, Direct Taxation, business structuring apart from financial consultation. Practicing since 2 decades in Bengaluru, developed team of professionals to provide holistic and 360 Degree services to the clients. Living with parents, View Full Profile

My Published Posts

Quarterly updates under RERA – mandatory compliance under RERA 7 Years of RERA: Building Trust, Transparency & Transformation in Real Estate Changes in Real Estate Business Post implimentation of RERA RERA and importance of Financial Year End Reconciliation Recent Penalties by Karnataka RERA for Non-compliances View More Published Posts

Join Taxguru’s Network for Latest updates on Income Tax, GST, Company Law, Corporate Laws and other related subjects.

One Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Sponsored
Sponsored
Search Post by Date
July 2024
M T W T F S S
1234567
891011121314
15161718192021
22232425262728
293031